What delayed Alberta carbon capture project: analysts

Darpan News Desk The Canadian Press, 03 May, 2024 10:45 AM
  • What delayed Alberta carbon capture project: analysts

 

Capital Power's decision not to pursue its $2.4-billion Genesee project is unlikely to be the first of other such cancellations, said Scott MacDougall of the Pembina Institute, a clean energy think tank.

"I think (Genesee) is different enough that I wouldn't extrapolate too much," MacDougall said.

But Sara Hastings-Simon, who studies energy transition at the University of Calgary, said the backtracking underlines that, unlike some decarbonization strategies, carbon capture adds cost.

"When some people say this is going to be a big part of our decarbonization solution, the question is who's going to pay for it." 

And Thomas Timmins, head of energy practice for the law firm Gowling WLG, called Capital Power's decision a reminder that carbon capture technology is still new.

"It is not where the proponents of the technology might wish it were," Timmins said.

Carbon capture separates climate-changing gases such as carbon dioxide from exhaust and sequesters it deep underground. Industries from cement manufacture to the oilsands consider it one of the most promising ways to reduce their carbon emissions.  

Capital Power announced Wednesday it would no longer pursue carbon capture at its Genesee power plant near Edmonton because the economics no longer work. 

The decision removed Canada's largest such project from the books. Genesee would have stored three million tonnes of carbon dioxide a year -- about three times the storage rate of Shell's Quest project. 

In a conference call with analysts Wednesday, Capital Power CEO Avik Dey said the technology has a future. 

"I do feel strongly that carbon capture and sequestration works," he said.

But several factors convinced the company to pull the plug -- the uncertainty over how much Capital Power could earn from the carbon credits the project would generate, the amount of carbon price it would avoid and the cost per tonne of the captured carbon.

"I wouldn't say it's any one thing," he said. "We need all of it to work.

"What will unlock carbon capture and storage for natural gas is the (cost per unit of carbon) coming down such that we can work within whatever regulatory framework exists. We're just early."

Capital Power would have been the first natural gas plant to use the technology. That creates risks and adds costs, MacDougall said. 

"There would be some extra costs relative to the second or third project. Costs will come down for future deployments."

The process is better understood in other applications, he said.

"(Carbon capture) on gas turbines is quite different than (carbon capture) on gas boilers."

Another risk is that other carbon capture projects planned for Alberta could flood the market for the credits carbon capture would generate, lowering their value. 

Hastings-Simon said Alberta could address that risk by tightening up its industrial carbon emissions program. 

Making credits harder to earn would ensure their continuing value, she said. So would increasing the market by lowering emissions caps for other industries. 

"If you're willing to do that as a government, you can pretty much control that risk."

Governments can also guarantee companies an adequate floor price for the carbon credits they generate. 

But failing a groundbreaking technological innovation, Timmins said carbon capture will continue to need public support for projects to go ahead.

"It hasn't reached the level where it's commercially viable, yet," Timmins said. 

"What's needed? Either a breakthrough or government money."

 

MORE National ARTICLES

Talks fail to avert Vancouver transit strike, paralyzing bus and SeaBus service

Talks fail to avert Vancouver transit strike, paralyzing bus and SeaBus service
Metro Vancouver has been left without most bus services and SeaBus after weekend talks between transit supervisors and the Coast Mountain Bus Company broke down without a deal. TransLink says bus routes operated by Coast Mountain stopped running at 1 a.m. and SeaBus sailings for the morning have also been cancelled.

Talks fail to avert Vancouver transit strike, paralyzing bus and SeaBus service

Tens of thousands of Ukrainians expected to come to Canada in the next few months

Tens of thousands of Ukrainians expected to come to Canada in the next few months
Settlement agencies are preparing for the arrival of tens of thousands of Ukrainians before the end-of-March deadline for those fleeing the Russian invasion to enter Canada on emergency visas. The federal government has issued 936,293 temporary emergency visas since March 2022 for Ukrainians who want to work or study in Canada while they wait out the war. A total of 210,178 people had actually made the journey to Canada as of Nov. 28.

Tens of thousands of Ukrainians expected to come to Canada in the next few months

Surrey man wanted on outstanding arrest warrants in custody

Surrey man wanted on outstanding arrest warrants in custody
Surrey RCMP say a man who was wanted on outstanding arrest warrants is in custody. Police said last week they were looking for the 24-year-old, who was allegedly seen in September driving dangerously through Surrey's streets at peak traffic hours.

Surrey man wanted on outstanding arrest warrants in custody

Metro Vancouver bus union warns of service shutdown without deal with employer

Metro Vancouver bus union warns of service shutdown without deal with employer
The union representing transit supervisors in British Columbia's Lower Mainland says it will be “withdrawing all services” on Monday if an agreement with Coast Mountain Bus Company isn't made. CUPE Local 4500, representing more than 180 bus workers, says it has been waiting more than four weeks for Coast Mountain to respond to its latest proposal.    

Metro Vancouver bus union warns of service shutdown without deal with employer

Man dies after being hit by a snowplow

Man dies after being hit by a snowplow
Police in Abbotsford say a 31-year-old man is dead after being hit by a snowplow this morning. Officers say the man lost control of his vehicle on Highway 1 and went into the ditch.

Man dies after being hit by a snowplow

Four children with strep A have died in B.C. in the past month, disease centre says

Four children with strep A have died in B.C. in the past month, disease centre says
Four children under the age of 10 who had streptococcal infections have died since mid-December, in what the BC Centre for Disease Control says is part of a surge in such infections. A bulletin released by the centre, the Provincial Health Services Authority and BC Children's Hospital says data from 2023 show a three-fold increase in invasive group A streptococcal infections in people under 20. 

Four children with strep A have died in B.C. in the past month, disease centre says