Close X
Wednesday, September 18, 2024
ADVT 
National

What delayed Alberta carbon capture project: analysts

Darpan News Desk The Canadian Press, 03 May, 2024 10:45 AM
  • What delayed Alberta carbon capture project: analysts

 

Capital Power's decision not to pursue its $2.4-billion Genesee project is unlikely to be the first of other such cancellations, said Scott MacDougall of the Pembina Institute, a clean energy think tank.

"I think (Genesee) is different enough that I wouldn't extrapolate too much," MacDougall said.

But Sara Hastings-Simon, who studies energy transition at the University of Calgary, said the backtracking underlines that, unlike some decarbonization strategies, carbon capture adds cost.

"When some people say this is going to be a big part of our decarbonization solution, the question is who's going to pay for it." 

And Thomas Timmins, head of energy practice for the law firm Gowling WLG, called Capital Power's decision a reminder that carbon capture technology is still new.

"It is not where the proponents of the technology might wish it were," Timmins said.

Carbon capture separates climate-changing gases such as carbon dioxide from exhaust and sequesters it deep underground. Industries from cement manufacture to the oilsands consider it one of the most promising ways to reduce their carbon emissions.  

Capital Power announced Wednesday it would no longer pursue carbon capture at its Genesee power plant near Edmonton because the economics no longer work. 

The decision removed Canada's largest such project from the books. Genesee would have stored three million tonnes of carbon dioxide a year -- about three times the storage rate of Shell's Quest project. 

In a conference call with analysts Wednesday, Capital Power CEO Avik Dey said the technology has a future. 

"I do feel strongly that carbon capture and sequestration works," he said.

But several factors convinced the company to pull the plug -- the uncertainty over how much Capital Power could earn from the carbon credits the project would generate, the amount of carbon price it would avoid and the cost per tonne of the captured carbon.

"I wouldn't say it's any one thing," he said. "We need all of it to work.

"What will unlock carbon capture and storage for natural gas is the (cost per unit of carbon) coming down such that we can work within whatever regulatory framework exists. We're just early."

Capital Power would have been the first natural gas plant to use the technology. That creates risks and adds costs, MacDougall said. 

"There would be some extra costs relative to the second or third project. Costs will come down for future deployments."

The process is better understood in other applications, he said.

"(Carbon capture) on gas turbines is quite different than (carbon capture) on gas boilers."

Another risk is that other carbon capture projects planned for Alberta could flood the market for the credits carbon capture would generate, lowering their value. 

Hastings-Simon said Alberta could address that risk by tightening up its industrial carbon emissions program. 

Making credits harder to earn would ensure their continuing value, she said. So would increasing the market by lowering emissions caps for other industries. 

"If you're willing to do that as a government, you can pretty much control that risk."

Governments can also guarantee companies an adequate floor price for the carbon credits they generate. 

But failing a groundbreaking technological innovation, Timmins said carbon capture will continue to need public support for projects to go ahead.

"It hasn't reached the level where it's commercially viable, yet," Timmins said. 

"What's needed? Either a breakthrough or government money."

 

MORE National ARTICLES

London Drugs phone lines working, stores still closed after cybersecurity incident

London Drugs phone lines working, stores still closed after cybersecurity incident
London Drugs says its phone lines are working again after being taken offline in response to a cybersecurity incident. A statement from the Richmond, B.C.-based pharmacy and retail chain says Canada Post offices inside London Drugs stores are also up and running again.

London Drugs phone lines working, stores still closed after cybersecurity incident

Macklem says he doesn't think federal budget will have much of an impact on inflation

Macklem says he doesn't think federal budget will have much of an impact on inflation
Bank of Canada governor Tiff Macklem said he doesn't think the federal budget tabled last month will have much of an effect on inflation. Macklem was testifying at a Senate committee alongside senior deputy governor Carolyn Rogers on Wednesday following the central bank's latest interest rate announcement.

Macklem says he doesn't think federal budget will have much of an impact on inflation

B.C. launches portal to help find hotel rooms for emergency evacuees

B.C. launches portal to help find hotel rooms for emergency evacuees
British Columbia's hotel association says a new central booking portal will help speed up the process of finding places to stay for emergency evacuees. A statement says the system launching in June will provide provincial emergency support staff with live information on room availability, eliminating the need to call hotels to find out. 

B.C. launches portal to help find hotel rooms for emergency evacuees

Woman with a knife arrested at New Westminster post-secondary school

Woman with a knife arrested at New Westminster post-secondary school
Police in New Westminster, B.C., say they were called to a post-secondary school in the city when staff reported that a woman armed with a knife was inside the building. The woman was not a student at the institution and police say students and staff feared for their safety. 

Woman with a knife arrested at New Westminster post-secondary school

B.C's auditor general to review government's response to 2021 Lytton wildfire

B.C's auditor general to review government's response to 2021 Lytton wildfire
British Columbia's auditor general says his office is doing a review of the province's response to the 2021 wildfire that devastated the community of Lytton, B.C. Michael Pickup says in a video statement that the report will focus on the B.C. government's roles and responsibilities for disaster recovery, its support for Lytton, including funding, challenges that came with rebuilding and how the province can improve.

B.C's auditor general to review government's response to 2021 Lytton wildfire

LNG company's plan for floating work camp is rejected by Squamish, B.C.

LNG company's plan for floating work camp is rejected by Squamish, B.C.
Plans to use a renovated cruise ship to house more than 600 workers as they build a liquefied natural gas facility near Squamish, B.C., have been voted down by the local council. The ship arrived in B.C. waters in January after a 40-day journey from Estonia, where it had sheltered Ukrainian refugees, but Woodfibre LNG didn't obtain a permit from the district to operate the so-called "floatel."

LNG company's plan for floating work camp is rejected by Squamish, B.C.