Premier Warns NDP, Greens That Delaying Site C Dam In B.C. Could Cost $600M

Darpan News Desk The Canadian Press, 07 Jun, 2017 01:16 PM
    VANCOUVER — British Columbia's political leaders exchanged duelling letters over the future of the Site C dam project on Tuesday, with Premier Christy Clark arguing that delays will cost hundreds of millions of dollars.
     
    NDP Leader John Horgan wrote to BC Hydro last week asking it to suspend the evictions of two homeowners and urging it not to sign any new contracts on the $8.8-billion hydroelectric dam until a new government has gained the confidence of the legislature.
     
    But Clark says in letters sent to Horgan and Green Leader Andrew Weaver that the evictions are necessary as part of a road and bridge construction project that are needed to divert a river in September 2019.
     
    Any delay could postpone the diversion by a year and cost taxpayers $600 million, she says.
     
    "With a project of this size and scale, keeping to a tight schedule is critical to delivering a completed project on time and on budget," she says. "The requests contained in your letter are not without consequences to the construction schedule and ultimately have financial ramifications to ratepayers."
     
    The premier has asked Horgan and Weaver to reply by Saturday on whether they still want to put the evictions on hold. She says a decision to proceed must be made by June 15 in order to maintain the river diversion schedule.
     
    She also asks whether they want the government to issue a "tools down" request to BC Hydro on other decisions that she says are essential to maintaining the budget and construction schedule.
     
     
    In his reply, Horgan writes he was surprised to receive the letter from Clark.
     
    "In it, you made unsupported claims about additional costs associated with asking BC Hydro not to sign major contracts until a new government takes office," he says.
     
    "If you are truly concerned about this timeline, there is a simple solution: recall the legislature immediately and face a confidence vote so British Columbians can get the new government they voted for."
     
    An agreement between the NDP and Green party was signed last week that would allow the New Democrats to form a minority government, ousting Clark's Liberals.
     
    The agreement includes a promise to refer the Site C project to the B.C. Utilities Commission to determine its economic viability.
     
    But Clark says the project is likely to progress past the "point of no return" before a review can be completed.
     
    Clark didn't define what she meant by "point of no return," nor did she explain how she reached the $600-million figure in her letter. Her press secretary Stephen Smart referred questions to BC Hydro, which declined to answer them and instead sent an emailed statement.
     
    "BC Hydro is aware of the letters sent by Premier Clark to the leader of the B.C. NDP and the leader of the provincial Green party. We have no further comment at this time," it said.
     
    Weaver issued his own letter that says before he can comment on Clark's assertions he requires access to supporting evidence, including signed contracts, the project schedule and potential alternative project timelines.
     
    "Your government is turning a significant capital project that potentially poses massive economic risks to British Columbians into a political debate rather than one informed by evidence and supported by independent analysis."
     
     
    The dam will be the third on the Peace River, flooding an 83-kilometre stretch of valley, and local First Nations, landowners and farmers have fiercely opposed the project.
     
    Construction began two years ago and the project employs more than 2,000 people.
     
    A report by University of British Columbia researchers in April argued it wasn't too late to press pause on the project and that the electricity produced by Site C won't be fully required for nearly a decade after it's complete. It said cancelling the project as of June 30 would save between $500 million and $1.65 billion.

    MORE National ARTICLES

    British Columbia New Democrats Promise Balanced Budget, Higher Corporate Tax

    British Columbia New Democrats Promise Balanced Budget, Higher Corporate Tax
    COQUITLAM, B.C. — British Columbia's New Democrats are promising three years of balanced budgets while also reining in auto insurance rates and BC Ferries fares if they win the provincial election.

    British Columbia New Democrats Promise Balanced Budget, Higher Corporate Tax

    Five Things To Consider About The Liberal Government's Plan To Legalize Pot

    Five Things To Consider About The Liberal Government's Plan To Legalize Pot
    The Liberal government introduced long-awaited legislation Thursday to legalize the recreational use of marijuana, but many of the finer points and logistical questions remain unanswered or up in the air. Here are five of them

    Five Things To Consider About The Liberal Government's Plan To Legalize Pot

    Trudeau, Take Up Malala Yousafzai's Challenge For Leadership On Education: Ambrose

    Trudeau, Take Up Malala Yousafzai's Challenge For Leadership On Education: Ambrose
    OTTAWA — Interim Conservative leader Rona Ambrose wants Prime Minister Justin Trudeau to answer Pakistani activist Malala Yousafzai's call to put advancing girls' education at the heart of Canada's turn at the helm of the G7.

    Trudeau, Take Up Malala Yousafzai's Challenge For Leadership On Education: Ambrose

    WATCH: PM Justin Trudeau Wins Hearts Again, Wishes Everyone Happy Baisakhi In Fluent Punjabi

    WATCH: PM Justin Trudeau Wins Hearts Again, Wishes Everyone Happy Baisakhi In Fluent Punjabi
    Here's Him Wishing Everyone A Very Happy Vaisakhi, In Punjabi! Yup, You Read That Right! 

    WATCH: PM Justin Trudeau Wins Hearts Again, Wishes Everyone Happy Baisakhi In Fluent Punjabi

    Vaisakhi Spotlight: Jagmeet Singh Dhaliwal - Leading with Style

    Vaisakhi Spotlight: Jagmeet Singh Dhaliwal -  Leading with Style
    A former criminal defence lawyer, it was Dhaliwal’s profession that led him onto the path of a political career. 

    Vaisakhi Spotlight: Jagmeet Singh Dhaliwal - Leading with Style

    Amandeep Bath Murder: Parminder Basran, Bhabjit Aujla Sentenced

    Amandeep Bath Murder: Parminder Basran, Bhabjit Aujla Sentenced
    Parminder Singh Basran pleaded guilty to manslaughter in B.C. Provincial Court in New Westminster and Bhabjit Singh Aujla pleaded guilty to assault on March 3.

    Amandeep Bath Murder: Parminder Basran, Bhabjit Aujla Sentenced