Premier Warns NDP, Greens That Delaying Site C Dam In B.C. Could Cost $600M

Darpan News Desk The Canadian Press, 07 Jun, 2017 01:16 PM
    VANCOUVER — British Columbia's political leaders exchanged duelling letters over the future of the Site C dam project on Tuesday, with Premier Christy Clark arguing that delays will cost hundreds of millions of dollars.
     
    NDP Leader John Horgan wrote to BC Hydro last week asking it to suspend the evictions of two homeowners and urging it not to sign any new contracts on the $8.8-billion hydroelectric dam until a new government has gained the confidence of the legislature.
     
    But Clark says in letters sent to Horgan and Green Leader Andrew Weaver that the evictions are necessary as part of a road and bridge construction project that are needed to divert a river in September 2019.
     
    Any delay could postpone the diversion by a year and cost taxpayers $600 million, she says.
     
    "With a project of this size and scale, keeping to a tight schedule is critical to delivering a completed project on time and on budget," she says. "The requests contained in your letter are not without consequences to the construction schedule and ultimately have financial ramifications to ratepayers."
     
    The premier has asked Horgan and Weaver to reply by Saturday on whether they still want to put the evictions on hold. She says a decision to proceed must be made by June 15 in order to maintain the river diversion schedule.
     
    She also asks whether they want the government to issue a "tools down" request to BC Hydro on other decisions that she says are essential to maintaining the budget and construction schedule.
     
     
    In his reply, Horgan writes he was surprised to receive the letter from Clark.
     
    "In it, you made unsupported claims about additional costs associated with asking BC Hydro not to sign major contracts until a new government takes office," he says.
     
    "If you are truly concerned about this timeline, there is a simple solution: recall the legislature immediately and face a confidence vote so British Columbians can get the new government they voted for."
     
    An agreement between the NDP and Green party was signed last week that would allow the New Democrats to form a minority government, ousting Clark's Liberals.
     
    The agreement includes a promise to refer the Site C project to the B.C. Utilities Commission to determine its economic viability.
     
    But Clark says the project is likely to progress past the "point of no return" before a review can be completed.
     
    Clark didn't define what she meant by "point of no return," nor did she explain how she reached the $600-million figure in her letter. Her press secretary Stephen Smart referred questions to BC Hydro, which declined to answer them and instead sent an emailed statement.
     
    "BC Hydro is aware of the letters sent by Premier Clark to the leader of the B.C. NDP and the leader of the provincial Green party. We have no further comment at this time," it said.
     
    Weaver issued his own letter that says before he can comment on Clark's assertions he requires access to supporting evidence, including signed contracts, the project schedule and potential alternative project timelines.
     
    "Your government is turning a significant capital project that potentially poses massive economic risks to British Columbians into a political debate rather than one informed by evidence and supported by independent analysis."
     
     
    The dam will be the third on the Peace River, flooding an 83-kilometre stretch of valley, and local First Nations, landowners and farmers have fiercely opposed the project.
     
    Construction began two years ago and the project employs more than 2,000 people.
     
    A report by University of British Columbia researchers in April argued it wasn't too late to press pause on the project and that the electricity produced by Site C won't be fully required for nearly a decade after it's complete. It said cancelling the project as of June 30 would save between $500 million and $1.65 billion.

    MORE National ARTICLES

    Indian-Origin Google Researcher Neel Mehta Links Ransomware Attack To N.Korea

    Indian-Origin Google Researcher Neel Mehta Links Ransomware Attack To N.Korea
    As the world struggles to identify the cybercriminals behind the global ransowmware attack that hit 150 countries over the weekend, Neel Mehta, an Indian-origin security researcher working with Google, has claimed on Twitter that the hackers may have links to North Korea.

    Indian-Origin Google Researcher Neel Mehta Links Ransomware Attack To N.Korea

    Aga Khan Opens Ottawa Pluralism Centre, As Trudeau Chopper Controversy Swirls

    OTTAWA — The Aga Khan returned Tuesday to Ottawa to unveil the new headquarters of an international organization that is positioning itself as an antidote of sorts to growing strains of populism and intolerance around the world.

    Aga Khan Opens Ottawa Pluralism Centre, As Trudeau Chopper Controversy Swirls

    Man Offers 'Apology Beer' After Drunken Break-in Attempt At Halifax Apartment

    Man Offers 'Apology Beer' After Drunken Break-in Attempt At Halifax Apartment
    Caitlynne Hines said a drunk man attempted to enter her north end apartment on May 5, insisting a friend was staying at the apartment upstairs.

    Man Offers 'Apology Beer' After Drunken Break-in Attempt At Halifax Apartment

    Jagmeet Singh Steps Down As Ontario NDP Deputy Leader During Federal Bid

    Jagmeet Singh Steps Down As Ontario NDP Deputy Leader During Federal Bid
    Jagmeet Singh is stepping down as deputy leader of the Ontario NDP while he runs for the federal party's leadership, but he's not resigning his seat in the provincial legislature.

    Jagmeet Singh Steps Down As Ontario NDP Deputy Leader During Federal Bid

    Three Accused In Murder Of B.C. Gangster Want Case Tossed Over Delays

    Three Accused In Murder Of B.C. Gangster Want Case Tossed Over Delays
    Surrey's Jujhar Singh Khun-Khun, 25, has been charged with first-degree murder and attempted murder in relation to the 2011 shooting death of gangster Jonathan Bacon in Kelowna. Khun-Khun is being charged alongside two other men.

    Three Accused In Murder Of B.C. Gangster Want Case Tossed Over Delays

    Women-only Overdose Prevention Site Opens On Vancouver's Downtown Eastside

    VANCOUVER — A safe injection site that will only serve women has opened on Vancouver's Downtown Eastside.

    Women-only Overdose Prevention Site Opens On Vancouver's Downtown Eastside