Darpan News Desk The Canadian Press, 24 Jun, 2016 11:45 AM
    ST. JOHN'S, N.L. — Estimated costs for the troubled Muskrat Falls hydro megaproject in Labrador have now hit $11.4 billion including financing.
     
    That's up from an original estimate of $7.4 billion -- including the cost of borrowing -- when the development was sanctioned in 2012.
     
    First power from the dam and hydro station under construction on the lower Churchill River was expected next year, but Nalcor Energy CEO Stan Marshall now says first power is delayed until the fall of 2019.
     
    "In my opinion the Muskrat Falls project was not the right choice," Marshall told a news conference Friday.
     
    Still, he said he expects the project will "finish strong."
     
    Full power from Muskrat Falls to the island of Newfoundland and on to Nova Scotia through subsea cables is expected in mid-2020.
     
    Marshall says original cost estimates were optimistic or overly aggressive.
     
    He also says some contractors lacked experience working in harsh environments and that early execution by some "was poor."
     
    About $6.7 billion has been spent or is already committed to the project.
     
    Marshall says most problems stem from construction of the power plant. He says Nalcor is in "a major dispute" with construction contractor Astaldi Canada. He said it's the major uncertainty for Muskrat Falls but that talks continue.
     
    Marshall says electricity rates for domestic customers are now expected to rise to 21.4 cents per kilowatt hour in 2021, before tax. That's up 6.3 cents from forecasts when the project was sanctioned in 2012.
     
    Sales of available export power would bring those estimates down by less than a cent, Marshall predicted.
     
    Consumers in the province paid about 12 cents per kilowatt hour last year before tax. That compares to almost 15 cents in Ontario and 16 cents in Nova Scotia.
     
    Marshall says forecasted energy needs have decreased, but the province still needs a new source of power to replace the aging Holyrood plant and to meet future demand.
     
    He predicts by the time Muskrat Falls comes onstream, consumers in the province will be paying among the highest rates in the country.
     
    Still, Marshall — who took over just two months ago as CEO of the project, which was sanctioned by the former PC government — says it's too late to turn back.
     
    "It was a gamble," Marshall said of energy price assumptions made when the project was approved.
     
    "And it has gone against us."
     
     
    The province is obligated to provide power to Nova Scotia utility Emera for 35 years. Nixing Muskrat Falls and myriad contracts would be far more expensive than forging ahead, he said.
     
    "The project was too big for our needs," says Marshall. "We speculated, and we lost."
     
    Premier Dwight Ball said he wouldn't go so far as to describe Muskrat Falls as a "boondoggle" as Marshall did.
     
    But he said he can understand if people question why they should trust anything they hear from Nalcor Energy.
     
    "I completely understand why people would look at the project and say: 'I've heard this before. It's political.'
     
    "We're going to see it past the finish line. Underpinning it will be reliable power at competitive prices."
     
    Ball said he'll work with Marshall over the next four years to find ways to lower Muskrat Falls power rates for consumers.
     
    "We've inherited this project. We've inherited the challenges that come with it."

    MORE National ARTICLES

    Privacy Laws, Bureaucracy Make Canada A Challenging Place For Solving Cold Cases

    Privacy Laws, Bureaucracy Make Canada A Challenging Place For Solving Cold Cases
    He mapped her movements through her downtown neighbourhood, plotted his attack, then savagely struck one August night in 1983. When he was done, Susan Tice lay sexually assaulted, stabbed and breathing her last in her own bedroom.

    Privacy Laws, Bureaucracy Make Canada A Challenging Place For Solving Cold Cases

    University Of Calgary Pays Ransom Of $20,000 After Attack On Computer Systems

    University Of Calgary Pays Ransom Of $20,000 After Attack On Computer Systems
    The University of Calgary says it paid a ransom of $20,000 demanded after a recent cyberattack to preserve an option to restore critical research data.

    University Of Calgary Pays Ransom Of $20,000 After Attack On Computer Systems

    Giant Sinkhole Opens Up In Ottawa Street

    Giant Sinkhole Opens Up In Ottawa Street
      Water could be seen gushing through the sinkhole before crews managed to shut the water off.

    Giant Sinkhole Opens Up In Ottawa Street

    Group Wants Liberals To Take Action On Plan To Help Yazidi Refugees

    Group Wants Liberals To Take Action On Plan To Help Yazidi Refugees
    OTTAWA — At least 400 Yazidi women raped and tortured by Islamic militants could have safe passage to Canada if the government would heed a proposal to rescue them, a religious freedoms organization says.

    Group Wants Liberals To Take Action On Plan To Help Yazidi Refugees

    Pan Am Games $342 MillionOver Budget: Ontario Auditor General

    TORONTO — Ontario's auditor general says last summer's Pan Am and Parapan Am Games in Toronto came in $342 million over budget, but the province still paid more than $5 million in performance bonuses.

    Pan Am Games $342 MillionOver Budget: Ontario Auditor General

    Halifax Collector Wins Legal Battle With Canada Post Over Hockey Card

    Halifax Collector Wins Legal Battle With Canada Post Over Hockey Card
    HALIFAX — An avid eBay bidder in Halifax has won a legal battle against Canada Post over a mangled Conner McDavid hockey card.

    Halifax Collector Wins Legal Battle With Canada Post Over Hockey Card