    ST. JOHN'S, N.L. — Estimated costs for the troubled Muskrat Falls hydro megaproject in Labrador have now hit $11.4 billion including financing.
     
    That's up from an original estimate of $7.4 billion -- including the cost of borrowing -- when the development was sanctioned in 2012.
     
    First power from the dam and hydro station under construction on the lower Churchill River was expected next year, but Nalcor Energy CEO Stan Marshall now says first power is delayed until the fall of 2019.
     
    "In my opinion the Muskrat Falls project was not the right choice," Marshall told a news conference Friday.
     
    Still, he said he expects the project will "finish strong."
     
    Full power from Muskrat Falls to the island of Newfoundland and on to Nova Scotia through subsea cables is expected in mid-2020.
     
    Marshall says original cost estimates were optimistic or overly aggressive.
     
    He also says some contractors lacked experience working in harsh environments and that early execution by some "was poor."
     
    About $6.7 billion has been spent or is already committed to the project.
     
    Marshall says most problems stem from construction of the power plant. He says Nalcor is in "a major dispute" with construction contractor Astaldi Canada. He said it's the major uncertainty for Muskrat Falls but that talks continue.
     
    Marshall says electricity rates for domestic customers are now expected to rise to 21.4 cents per kilowatt hour in 2021, before tax. That's up 6.3 cents from forecasts when the project was sanctioned in 2012.
     
    Sales of available export power would bring those estimates down by less than a cent, Marshall predicted.
     
    Consumers in the province paid about 12 cents per kilowatt hour last year before tax. That compares to almost 15 cents in Ontario and 16 cents in Nova Scotia.
     
    Marshall says forecasted energy needs have decreased, but the province still needs a new source of power to replace the aging Holyrood plant and to meet future demand.
     
    He predicts by the time Muskrat Falls comes onstream, consumers in the province will be paying among the highest rates in the country.
     
    Still, Marshall — who took over just two months ago as CEO of the project, which was sanctioned by the former PC government — says it's too late to turn back.
     
    "It was a gamble," Marshall said of energy price assumptions made when the project was approved.
     
    "And it has gone against us."
     
     
    The province is obligated to provide power to Nova Scotia utility Emera for 35 years. Nixing Muskrat Falls and myriad contracts would be far more expensive than forging ahead, he said.
     
    "The project was too big for our needs," says Marshall. "We speculated, and we lost."
     
    Premier Dwight Ball said he wouldn't go so far as to describe Muskrat Falls as a "boondoggle" as Marshall did.
     
    But he said he can understand if people question why they should trust anything they hear from Nalcor Energy.
     
    "I completely understand why people would look at the project and say: 'I've heard this before. It's political.'
     
    "We're going to see it past the finish line. Underpinning it will be reliable power at competitive prices."
     
    Ball said he'll work with Marshall over the next four years to find ways to lower Muskrat Falls power rates for consumers.
     
    "We've inherited this project. We've inherited the challenges that come with it."

    MORE National ARTICLES

    Highway Of Tears Bus Service To Run From Prince George To Prince Rupert

    Highway Of Tears Bus Service To Run From Prince George To Prince Rupert
    Eighteen women have been murdered or have disappeared along Highway 16 between Prince George and Prince Rupert and adjacent routes since the 1970s.

    Highway Of Tears Bus Service To Run From Prince George To Prince Rupert

    Calgary Police Lay Several Charges Against Their Own After Anti-Corruption Probe

    Calgary Police Lay Several Charges Against Their Own After Anti-Corruption Probe
    Police say a woman came to them in August 2014 with allegations that she was being harassed by people she believed were hired by her former husband.

    Calgary Police Lay Several Charges Against Their Own After Anti-Corruption Probe

    A Third Of Canadian Kids Sleep Deprived, Most Get Too Much Screen Time: Report

    TORONTO — Almost a third of Canadian school-aged kids are sleep-deprived while most are spending too much time staring at screens, suggests an annual report on the state of children's health.

    A Third Of Canadian Kids Sleep Deprived, Most Get Too Much Screen Time: Report

    Home Renovation Expert And TV Host Mike Holmes Heading To Fort McMurray

    Home Renovation Expert And TV Host Mike Holmes Heading To Fort McMurray
    FORT MCMURRAY, Alta. — Canadian home renovation TV personality Mike Holmes says he will head to fire-ravaged Fort McMurray next week.

    Home Renovation Expert And TV Host Mike Holmes Heading To Fort McMurray

    Heavy Rains Cause Floods In Northeastern B.C., Damaging Rail Lines, Bridges

    Mayor Merlin Nichols of Chetwynd issued the declaration Wednesday after about 100 mm of rain drenched the town of about 3,000 people, 100 kilometres west of Dawson Creek.

    Heavy Rains Cause Floods In Northeastern B.C., Damaging Rail Lines, Bridges

    Ontario Woman Calls Police After Finding Venomous Scorpion In Bedroom

    Ontario Woman Calls Police After Finding Venomous Scorpion In Bedroom
    Police in Owen Sound say the venomous critter had escaped from another resident's home Tuesday, a day before it appeared in the woman's apartment.

    Ontario Woman Calls Police After Finding Venomous Scorpion In Bedroom