Close X
Saturday, November 23, 2024
ADVT 
National

Muskrat Falls Estimate Surpasses $11 Billion: 'Project Was Not The Right Choice'

Darpan News Desk The Canadian Press, 24 Jun, 2016 11:45 AM
    ST. JOHN'S, N.L. — Estimated costs for the troubled Muskrat Falls hydro megaproject in Labrador have now hit $11.4 billion including financing.
     
    That's up from an original estimate of $7.4 billion -- including the cost of borrowing -- when the development was sanctioned in 2012.
     
    First power from the dam and hydro station under construction on the lower Churchill River was expected next year, but Nalcor Energy CEO Stan Marshall now says first power is delayed until the fall of 2019.
     
    "In my opinion the Muskrat Falls project was not the right choice," Marshall told a news conference Friday.
     
    Still, he said he expects the project will "finish strong."
     
    Full power from Muskrat Falls to the island of Newfoundland and on to Nova Scotia through subsea cables is expected in mid-2020.
     
    Marshall says original cost estimates were optimistic or overly aggressive.
     
    He also says some contractors lacked experience working in harsh environments and that early execution by some "was poor."
     
    About $6.7 billion has been spent or is already committed to the project.
     
    Marshall says most problems stem from construction of the power plant. He says Nalcor is in "a major dispute" with construction contractor Astaldi Canada. He said it's the major uncertainty for Muskrat Falls but that talks continue.
     
    Marshall says electricity rates for domestic customers are now expected to rise to 21.4 cents per kilowatt hour in 2021, before tax. That's up 6.3 cents from forecasts when the project was sanctioned in 2012.
     
    Sales of available export power would bring those estimates down by less than a cent, Marshall predicted.
     
    Consumers in the province paid about 12 cents per kilowatt hour last year before tax. That compares to almost 15 cents in Ontario and 16 cents in Nova Scotia.
     
    Marshall says forecasted energy needs have decreased, but the province still needs a new source of power to replace the aging Holyrood plant and to meet future demand.
     
    He predicts by the time Muskrat Falls comes onstream, consumers in the province will be paying among the highest rates in the country.
     
    Still, Marshall — who took over just two months ago as CEO of the project, which was sanctioned by the former PC government — says it's too late to turn back.
     
    "It was a gamble," Marshall said of energy price assumptions made when the project was approved.
     
    "And it has gone against us."
     
     
    The province is obligated to provide power to Nova Scotia utility Emera for 35 years. Nixing Muskrat Falls and myriad contracts would be far more expensive than forging ahead, he said.
     
    "The project was too big for our needs," says Marshall. "We speculated, and we lost."
     
    Premier Dwight Ball said he wouldn't go so far as to describe Muskrat Falls as a "boondoggle" as Marshall did.
     
    But he said he can understand if people question why they should trust anything they hear from Nalcor Energy.
     
    "I completely understand why people would look at the project and say: 'I've heard this before. It's political.'
     
    "We're going to see it past the finish line. Underpinning it will be reliable power at competitive prices."
     
    Ball said he'll work with Marshall over the next four years to find ways to lower Muskrat Falls power rates for consumers.
     
    "We've inherited this project. We've inherited the challenges that come with it."

    MORE National ARTICLES

    B.C. Spring Tourism Growth Highest On Record

    From January to April, 1,172,637 visitors came to our province resulting in an 18.2% increase over the same period last year.

    B.C. Spring Tourism Growth Highest On Record

    Road Safety Improvements Coming To Popular B.C. Tourism Route Highway 20

    Road Safety Improvements Coming To Popular B.C. Tourism Route Highway 20
    Road improvements are coming to a popular tourism route between Bella Coola and Anahim Lake.

    Road Safety Improvements Coming To Popular B.C. Tourism Route Highway 20

    Winnepeg Jets T-Shirt Made By Company Licensed To Sell NHL Stock Shocker For Fan

    Winnepeg Jets T-Shirt Made By Company Licensed To Sell NHL Stock Shocker For Fan
    KELOWNA, B.C. — A life-long Winnipeg Jets fan was shocked to learn she'd bought a T-shirt with the city's name misspelled as Winnepeg.

    Winnepeg Jets T-Shirt Made By Company Licensed To Sell NHL Stock Shocker For Fan

    Surrey RCMP Welcomes New Summer Safety Specialist

    Surrey RCMP Welcomes New Summer Safety Specialist
    Surrey RCMP is saying goodbye for now to a unique Mountie who has helped us deal with the cold winter weather and hello, sunshine to a new face that will be joining us this summer.

    Surrey RCMP Welcomes New Summer Safety Specialist

    Province Adjusts Transit Fee For The Disabled, But Keeps Bus Pass Costs

    Province Adjusts Transit Fee For The Disabled, But Keeps Bus Pass Costs
    The provincial government website confirms the administration fee has been eliminated, but fees for a monthly pass that cost between $52 and $66 remains.

    Province Adjusts Transit Fee For The Disabled, But Keeps Bus Pass Costs

    Winnipeg Officer Makes Plea To Mom They Believe Abducted Her Children

    Winnipeg Officer Makes Plea To Mom They Believe Abducted Her Children
    Det. Sgt. Shaunna Neufeld spoke at a news briefing Thursday and asked Sandra Giesbrecht to get in touch with her.

    Winnipeg Officer Makes Plea To Mom They Believe Abducted Her Children