Kinder Morgan Pipeline Opponents Furious About 'Chaotic' Review Process

The Canadian Press, 30 Jul, 2015 04:54 PM
    VANCOUVER — Opponents of Kinder Morgan's plan to boost capacity of its Trans Mountain pipeline across southern B.C., accuse the National Energy Board of once again changing key dates in the review process.
     
    The NEB is due to release draft conditions for the pipeline on Aug. 12.
     
    Earlier this month it changed the deadline for letters of comment on the draft conditions from July 23 to Sept. 3, but the Sierra Club says the NEB has just issued a new deadline of Aug. 18.
     
    Sierra Club spokeswoman Larissa Stendie says that gives opponents just six days to respond and she calls the NEB handling of the pipeline review process "chaotic," "deeply flawed," and "unfair."
     
    She urges the energy board to stick to its Sept. 3 date, while other critics say the mid-August deadline raises concerns that any comments will be marginalized or ignored.
     
    NEB spokeswoman Tara O'Donovan says the date was initially changed to Sept. 3 in response to a motion from the City of Chilliwack to extend the deadline.
     
    Previously, commenters were expected to file their letters of comment before the draft conditions were released, she says.
     
    However, she says the deadline was changed to Aug. 18 to give time for interveners and Trans Mountain to respond to letters of comment in their written submissions.
     
    Trans Mountain must file its written argument by Aug. 20, and interveners must file their written argument on Sept. 3, she says.
     
    "We expect six days should be sufficient time for writers to provide comments on draft conditions in their letters of comment. If any comment writers do not view six days as providing enough time, they can request an extension," says O'Donovan.
     
    She says the online public registry has been updated to reflect the change and the board apologizes for any inconvenience caused by the matter.
     
    Kinder Morgan hopes to triple the bitumen-carrying capacity of the Trans Mountain line by laying almost 1,000 kilometres of new pipe between Edmonton and Metro Vancouver, increasing the number of tankers in Burrard Inlet to 34 from the current five per month.

    MORE National ARTICLES

    Audit Council Says B.C. Justified For Ousting Local Government Auditor General

    Through documents filed in the province's supreme Court, B.C.'s audit council fired back after former auditor general Basia Ruta filed a lawsuit against the group alleging wrongful dismissal.

    Audit Council Says B.C. Justified For Ousting Local Government Auditor General

    Case Dismissed Against Woman Charged In Death Of Lobster Fisherman Phillip Boudreau

    Carla Samson was facing a charge of accessory after the fact in the death of Phillip Boudreau, whose body was never found after he disappeared on June 1, 2013.

    Case Dismissed Against Woman Charged In Death Of Lobster Fisherman Phillip Boudreau

    Ontario Replacing Peeling Signs On Highway Lanes To Be Used During Pan Am

    Ontario Replacing Peeling Signs On Highway Lanes To Be Used During Pan Am
    TORONTO — Ontario's government says work will get underway as soon as possible to replace peeling signs marking temporary high-occupancy vehicle lanes in the Toronto region that will be used for the Pan Am Games.

    Ontario Replacing Peeling Signs On Highway Lanes To Be Used During Pan Am

    Canadian Pacific Challenging Responsibility In Lac-megantic Disaster In Court

    Canadian Pacific Challenging Responsibility In Lac-megantic Disaster In Court
    SHERBROOKE, Que. — A judge has begun hearing arguments that could determine the fate of more than $431 million destined for victims and creditors of the 2013 train disaster in Lac-Megantic, Que.

    Canadian Pacific Challenging Responsibility In Lac-megantic Disaster In Court

    Vancouver Residents Asked To Avoid Seawall After Apparent Diesel Spill In False Creek

    Vancouver Residents Asked To Avoid Seawall After Apparent Diesel Spill In False Creek
    Jeff Brady with the Canadian Coast Guard says hundreds of metres of containment booms have been set up off Granville Island.

    Vancouver Residents Asked To Avoid Seawall After Apparent Diesel Spill In False Creek

    RCMP Investigate Second Weekend Shooting In Surrey That Put Two More In Hospital

    RCMP Investigate Second Weekend Shooting In Surrey That Put Two More In Hospital
    RCMP say they responded to reports of gunfire between two vehicles (in the 18600 block of Highway 10) around 10 p.m. on Saturday.

    RCMP Investigate Second Weekend Shooting In Surrey That Put Two More In Hospital