Health Canada OKs GSK's plan to fix Quebec flu vaccine plant problems

Helen Branswell The Canadian Press, 11 Aug, 2014 03:42 PM
    TORONTO - Health Canada says it has approved a plan by GlaxoSmithKline to fix contamination problems it has been experiencing at its Ste. Foy, Que., flu vaccine production plant.
     
    The department says GSK's action plan and the timelines proposed in it are satisfactory.
     
    Inspections conducted this spring by the U.S. Food and Drug Administration and Health Canada identified problems at the facility largely related to bacterial contamination linked to the plant's water purification system.
     
    While the precise nature of the problems has not been make public, the FDA issued GSK a warning letter, the last step before possible suspension of a licence to supply to the U.S. market.
     
    And Health Canada's inspection report identified seven so-called major observations, things classified as signs that production is not consistently hitting required standards.
     
    The company was given a month to respond to the Health Canada report and did so on July 31.
     
    "We have completed the evaluation of GSK's action plan of its Ste. Foy facility, ID Biomedical. GSK's proposed approach and the timelines proposed have been deemed acceptable by Health Canada," the department said Monday via email.
     
    "We will monitor the progress of the implementation of the corrective action plan and conduct regular testing on lots of vaccine prior to their release onto the Canadian market."
     
    GSK declined to comment about its remediation plan, saying it would be inappropriate to speak publicly about an ongoing process.
     
    The FDA warning letter noted GSK has repeatedly been forced to discard batches of vaccine made at the facility because of bacterial counts that registered above specified limits. The letter, dated June 12, said 21 per cent of this year's product could not be released to the market.
     
    The plant, which GSK bought from ID Biomedical in late 2005, has contracts to produce 53 per cent of Canada's seasonal flu vaccine for the coming season as well as 23 million doses for the U.S. market. It is the only flu vaccine production facility located in Canada and holds the country's long-term pandemic flu vaccine contract.
     
    The FDA has already released for distribution two lots of vaccine from the Ste. Foy plant, GSK says. Flu vaccination programs typically begin in the United States in September, several weeks before the late October or early November launch in most Canadian provinces and territories.
     
    GSK has said in the past that fixing its production problems would not affect its ability to deliver flu vaccine for the Canadian market this fall.

    MORE National ARTICLES

    Canadian women do more household chores than men, says report

    Canadian women do more household chores than men, says report
    The latest findings by the Organization for Economic Co-operation and Development suggest that women in Canada carry out more household chores in an average week in comparison to men. 

    Canadian women do more household chores than men, says report

    Liberals propose changes to Temporary Foreign Worker Program

    Liberals propose changes to Temporary Foreign Worker Program
    Liberals have come forward proposing changes to the much debated Temporary Foreign Worker Program.

    Liberals propose changes to Temporary Foreign Worker Program

    Maharashtra train derailment kills 18

    Maharashtra train derailment kills 18
     Eighteen passengers were killed and more than 60 injured when the engine and four coaches of a passenger train derailed here in Maharashtra Sunday, Home Minister R.R. Patil said.

    Maharashtra train derailment kills 18

    Three Surrey men charged with violent sexual assaults

    Three Surrey men charged with violent sexual assaults
    Royal Canadian Mounted Police (RCMP) confirmed that three suspects identified as Simranpreet Dhillon, Sukhraj Chahal and Gurjinder Sodha were involved in two incidents in Surrey city 

    Three Surrey men charged with violent sexual assaults

    Political contemporaries demand resignation from Rob Ford

    Political contemporaries demand resignation from Rob Ford
    Political contemporaries and council colleagues are demanding a resignation from Toronto Mayor Rob Ford after Wednesday’s episode in which the media uncovered another video of him smoking crack cocaine.

    Political contemporaries demand resignation from Rob Ford

    Microsoft's new centre to generate 400 jobs in Vancouver

    Microsoft's new centre to generate 400 jobs in Vancouver
    Microsoft has announced plans to open a new training and development centre in Vancouver that will more than double its workforce thus creating 400 new jobs. The announcement that came in Thursday translates into posing Vancouver home to Microsoft's largest centre in Canada.

    Microsoft's new centre to generate 400 jobs in Vancouver