Government moves ahead on replacement for Massey Tunnel

Darpan News Desk BC Government, 09 Feb, 2022 04:10 PM
  • Government moves ahead on replacement for Massey Tunnel

Nine contracts have been awarded for technical and engineering expertise to support the Province’s delivery of the Highway 99 Tunnel Program to replace the Massey Tunnel, which will improve mobility along the corridor between Richmond and Delta.

“We are moving ahead with a new toll-free tunnel to replace the George Massey Tunnel, and these contracts will support the ministry’s work as we move from development to construction,” said Rob Fleming, Minister of Transportation and Infrastructure. “The new tunnel, along with a new Steveston Interchange and Highway 99 improvements, are being designed to improve safety, reliability and connectivity while aligning with regional interests.”

The following contracts with a total value of $56.7 million were awarded following the Province of B.C.’s thorough procurement process:

Owner's Engineering Service (Immersed Tube Tunnel):
COWI North America Ltd.
Value: $15,000,000

Owner's Engineering Service (Highway and Civil Works):
R.F. Binnie and Associates Ltd.  
Value: $15,000,000

Archaeological Services:
Golder Associates
Value: $2,100,000

Environmental Services:
Golder Associates
Value: $14,771,000

Independent Environmental Monitor for the Corridor Improvement Projects:
Sartori Environmental Inc.     
Value: $725,000

Marine Navigation Advisor:
TyPlan Consulting
Value: $322,000

Communication and Engagement Services (Highway 99 Tunnel Project/Steveston Interchange Project):
Lucent Quay Consulting Inc.
Value: $4,187,690

Hydrotechnical and River Hydraulics Services:
Northwest Hydraulic Consultants Ltd.
Value $4,400,000

Marine Construction Advisor:
RAM Engineering Ltd.
Value: $202,000

The Highway 99 Tunnel Program will result in travel-time savings in the region for vehicles, including buses, as well as providing new opportunities for people who cycle or walk. 

The next step in the Fraser River Tunnel Project is to initiate the environmental assessment process. This includes ongoing engagement with Indigenous groups and stakeholders and preparation for procurement. The new tunnel is estimated to cost $4.15 billion and is scheduled to be complete in 2030.

In the interim, improvements to transit and cycling infrastructure along Highway 99 are underway. Construction of the new Steveston Interchange is scheduled to begin this year.

Transportation Investment Corporation is leading the delivery of the major elements (eight-lane tunnel and Steveston Interchange) of the Highway 99 Tunnel Program on behalf of the Ministry of Transportation and Infrastructure, and will provide the controls, practices and other oversights essential for this complex project.

MORE National ARTICLES

No cause yet for Vancouver fire that killed three

No cause yet for Vancouver fire that killed three
Assistant Chief Brian Bertuzzi confirmed a child under 10 years old, their mother and grandfather were killed, while the grandmother and father suffered smoke inhalation.

No cause yet for Vancouver fire that killed three

Moderna announces full US approval for its COVID-19 vaccine

Moderna announces full US approval for its COVID-19 vaccine
The decision was bolstered by real-world evidence from the more than 200 million doses administered in the U.S. since the FDA cleared the shot in December 2020. The FDA granted full approval of Pfizer’s vaccine last August.

Moderna announces full US approval for its COVID-19 vaccine

Ottawa protests aren't 'peaceful': critics

Ottawa protests aren't 'peaceful': critics
For two days, the downtown core of the nation's capital has been a no-go zone as trucks and crowds have snarled traffic, with some members defacing monuments and wielding signs with violent and hateful imagery. Police are also investigating what they describe as threatening behaviour toward officers, city workers and other individuals, as well as damage to a city vehicle.

Ottawa protests aren't 'peaceful': critics

PM Justin Trudeau tests positive for COVID-19

PM Justin Trudeau tests positive for COVID-19
Trudeau is fully vaccinated and received his booster shot at a local Ottawa pharmacy in early January. Last Thursday, Trudeau said he was going into isolation for five days after finding out the previous evening he had been in contact with someone who tested positive.

PM Justin Trudeau tests positive for COVID-19

PBO puts estimate on feds' foreign homeowner tax

PBO puts estimate on feds' foreign homeowner tax
The one per cent tax was to take effect at the start of the year and the Finance Department estimates it will bring in $200 million in the 2022-2023 fiscal year, which begins in April.    

PBO puts estimate on feds' foreign homeowner tax

MPs to resume sitting as Ottawa protest simmers

MPs to resume sitting as Ottawa protest simmers
Prime Minister Justin Trudeau is set to address Canadians Monday afternoon, following three days of unrest that has brought the divisive arguments about vaccine mandates and public health restrictions soaring back to the top of the agenda.    

MPs to resume sitting as Ottawa protest simmers