Site C Construction Could Begin In 90 Days: BC Hydro Tells Communities

Darpan News Desk Darpan, 21 Oct, 2014 12:36 PM
    VANCOUVER - British Columbia's government has yet to announce a final decision on the Site C hydroelectric dam but BC Hydro has informed officials in the Peace River Valley that construction could begin in 90 days.
     
    The email from the project's senior environmental co-ordinator was sent out Friday to area municipal and aboriginal officials.
     
    Mayor Gwen Johansson says the email calls into question the repeat assurances from Energy Minister Bill Bennett that the provincial government has not made a final investment decision.
     
    The Crown agency must inform aboriginal and municipal agencies 90 days prior to the start of construction and BC Hydro says work will begin in January — subject to the final decision of cabinet to be announced by the end of the year.
     
    The $7.9-billion Site C dam would provide enough energy to power the equivalent of about 450,000 homes a year but it would also flood 55 square kilometres of river valley.
     
    The project received federal and provincial environmental approval earlier this month.

    MORE National ARTICLES

    No element of Canada's new prostitution law should target women, advocates say

    No element of Canada's new prostitution law should target women, advocates say
    No element of a proposed new prostitution law should criminalize prostitutes themselves, a coalition of women's groups said Wednesday.

    No element of Canada's new prostitution law should target women, advocates say

    Federal program focuses on "root causes" of missing aboriginal women

    Federal program focuses on
    One of the Conservative government's key programs on missing and murdered aboriginal women includes a focus on "addressing the root causes," despite the prime minister's suggestion that sociology isn't the right lens to use.

    Federal program focuses on "root causes" of missing aboriginal women

    BMO offers five-year, fixed mortgage rate of 2.99 per cent - again

    BMO offers five-year, fixed mortgage rate of 2.99 per cent - again
    The Bank of Montreal has slashed its five-year, fixed mortgage rate to 2.99 per cent, a level that had previously raised concerns about it leading to an overheated housing market.

    BMO offers five-year, fixed mortgage rate of 2.99 per cent - again

    New regulations must balance consumer, broadcaster needs, says BCE

    New regulations must balance consumer, broadcaster needs, says BCE
    Consumers will get less and pay more, and jobs will be lost, under proposals being debated this week to modernize television program delivery, the country's broadcast regulator has been told.

    New regulations must balance consumer, broadcaster needs, says BCE

    Stock up on ramen noodle: cost of university to rise 13 per cent over four years

    Stock up on ramen noodle: cost of university to rise 13 per cent over four years
    Students will need deeper pockets to study at Canadian universities over the next four years with annual fees projected to rise 13 per cent on average to $7,755, having almost tripled over the past 20 years, according to a new report.

    Stock up on ramen noodle: cost of university to rise 13 per cent over four years

    To Harper, finding Franklin ships as much about sovereignty as solving a mystery

    To Harper, finding Franklin ships as much about sovereignty as solving a mystery
    There are few things that turn Stephen Harper's crank as much as Canada's North.

    To Harper, finding Franklin ships as much about sovereignty as solving a mystery