B.C. Government Approves Construction Projects For $9-Billion Site C Hydro Dam

The Canadian Press, 08 Jul, 2015 10:54 AM
    FORT ST. JOHN, B.C. — The British Columbia government has granted approval for the first phase of construction to start on the massive Site C hydroelectric dam project on the Peace River.
     
    Two dozen authorizations include conditions under the land, water, forest and wildlife acts and provide permits for timber removal, road building and site preparation.
     
    Forests, Lands and Natural Resources Minister Steve Thomson said there were initially 45 permit applications submitted, but several of them were deferred to allow more time for consultations with First Nations.
     
    Thomson said each application for the construction phase was reviewed for its potential impact on the environment and on aboriginal treaty rights.
     
    All the decisions makers are satisfied that the consultation process was adequate and upholds the duty to consult local First Nations, Thomson said Tuesday.
     
    "A number of the permits have conditions attached to them that were concerns raised during that process," he said in a interview.
     
    Concerns include seasonal timing restrictions, conditions for wildlife, and the sharing of plans with First Nations, Thomson said.
     
    Consultations with the local Treaty 8 First Nation began in August 2014 and concluded last month, but Thomson wouldn't say if the two sides had reached a resolution.
     
    "We have been through the appropriate consultation process. As you know, concerns have been expressed by First Nations. We will see what the response to the decision is," he said.
     
    Several lawsuits by environmental groups, citizens and First Nations have been launched to try to stop construction of the dam and are proceeding through the courts.
     
    But Thomson said the legal action won't stop the building process.
     
    "This is a very, very important project for British Columbia. It has been through an environmental assessment process with conditions. The permits that are needed to get the initial process started have been through an extensive process."
     
    No one from the Treaty 8 First Nation was available for an interview.
     
    Construction of the almost $9-billion project is touted to generate about 10,000 jobs while it floods 55 square kilometres of river valley.  
     
    Site C represents an eight per cent increase to Hydro's energy supply and is expected to generate enough electricity to power about 450,000 homes per year.

    MORE National ARTICLES

    Alcohol A Factor In Mercedes-Porsche Crash That Killed One, Critically Injured One In Richmond: RCMP

    Alcohol A Factor In Mercedes-Porsche Crash That Killed One, Critically Injured One In Richmond: RCMP
    The collision sent the Porsche careening off road before it went airborne and slammed into a tree shortly before 10 p.m. on Saturday.

    Alcohol A Factor In Mercedes-Porsche Crash That Killed One, Critically Injured One In Richmond: RCMP

    Haze Of Wildfire Smoke Triggers Air Quality Advisory In Metro Vancouver

    Haze Of Wildfire Smoke Triggers Air Quality Advisory In Metro Vancouver
    The region's air quality department says high concentrations of fine particulate matter have been detected from wildfires burning in the surrounding area.

    Haze Of Wildfire Smoke Triggers Air Quality Advisory In Metro Vancouver

    Winnipeg Police Charge Guido Amsel, 49, In Bombing Of Law Firm

    Winnipeg Police Charge Guido Amsel, 49, In Bombing Of Law Firm
    Guido Amsel, 49, has been charged with two counts of attempted murder, one count of aggravated assault and a number of offences related to possessing explosives.

    Winnipeg Police Charge Guido Amsel, 49, In Bombing Of Law Firm

    Haze From B.C. Fires Makes Day Look Like Sunset, Others Forced To Flee

    Haze From B.C. Fires Makes Day Look Like Sunset, Others Forced To Flee
    The B.C. Wildfire Service says gusty winds and drought conditions are hampering efforts to contain dozens of wildfires in the province.

    Haze From B.C. Fires Makes Day Look Like Sunset, Others Forced To Flee

    Winnipeg Police Warn Justice Officials To Watch Their Mail For Next Day Or So

    Winnipeg police investigating the bombing of a law firm say if there are any more suspicious packages in the mail they will likely be found in the next day or so.

    Winnipeg Police Warn Justice Officials To Watch Their Mail For Next Day Or So

    Flood Mitigation, Infrastructure On The Agenda As PM Harper, Rachel Notley Meet In Calgary

    Flood Mitigation, Infrastructure On The Agenda As PM Harper, Rachel Notley Meet In Calgary
    CALGARY — Alberta Premier Rachel Notley says she plans to bring up flood mitigation with Prime Minister Stephen Harper during a meeting in Calgary.

    Flood Mitigation, Infrastructure On The Agenda As PM Harper, Rachel Notley Meet In Calgary