The Canadian Press, 19 Aug, 2015 10:30 AM
    VANCOUVER — Two northeastern British Columbia First Nations will suffer "irreparable harm" if thousands of hectares of old-growth forest are cleared to build the Site C dam, their lawyer says.
     
    John Gailus told B.C. Supreme Court that a stop-work order should be issued to halt the first phase of the nearly $9-billion hydroelectric project from proceeding along the Peace River.
     
    He said the Crown granted permits for the preparatory phase of construction without consulting with the West Moberly and Prophet River First Nations, which are members of the Treaty 8 Tribal Alliance.
     
    "The Crown truncated their consultation and issued the permits to meet an arbitrary timeline imposed by BC Hydro, we say, contrary to both its contractual obligations and its constitutional obligations," Gailus said Tuesday.
     
    The injunction application comes as the First Nations wait for both B.C. Supreme Court and Federal Court to deliver decisions on a judicial review aimed at quashing the hydroelectric project entirely.
     
    The provincial government granted approval in July for the first of seven construction phases, although the work hasn't yet started.
     
    Court heard the permits authorize the clearing of more than 1,600 hectares of forest, equivalent to about 4,500 truckloads of timber, along the south bank of the Peace River.
     
    Construction of new access roads and bridges, expansion of quarries and removal of beaver dams, eagle nests and the alteration of 163 archeological sites — which may include burial sites — was also authorized, Gailus said.
     
     
    He told court there's no urgency for starting the project.
     
    "There are significant benefits to the B.C. taxpayers for a delay," he said, adding costs will be higher if the work is allowed to move ahead and then the project is overturned.
     
    Outside court, West Moberly Chief Roland Willson called the consultation process a "farce."
     
    He said the First Nations signed an agreement in April to consult with the province on the first phase, but BC Hydro's permits were approved before any meetings.
     
    Willson was particularly concerned that up to 28 eagle nests would be destroyed.
     
    "It doesn't mean anything to anybody if we don't even talk about it and they approve (the permits)," he said. "We actually have to sit down and work through them together."
     
    Last month, Forests Minister Steve Thomson said each of the two dozen approved permit applications was reviewed for its potential impact on the environment and on aboriginal treaty rights.
     
    Thomson said the province conducted an "appropriate consultation process."
     
    BC Hydro expects construction of Site C to take at least a decade. The utility has said the project will power the equivalent of 450,000 homes per year.

    MORE National ARTICLES

    Son Of Former BC MLA, Kasimir Tyabji-Sandana, Charged In Fentanyl Bust Makes Court Appearance

    Son Of Former BC MLA, Kasimir Tyabji-Sandana, Charged In Fentanyl Bust Makes Court Appearance
    Kasimir Tyabji-Sandana, who is  27, is charged with one count of importing a controlled substance and will remain in custody until his next court appearance on Sept. 16.

    Son Of Former BC MLA, Kasimir Tyabji-Sandana, Charged In Fentanyl Bust Makes Court Appearance

    Second Degree Murder Charge Laid Against Brampton Man In The Death Of His Mother

    Second Degree Murder Charge Laid Against Brampton Man In The Death Of His Mother
    The 23-year-old suspect was arrested Saturday, a few hours after the body of his mother was discovered in a Brampton home.

    Second Degree Murder Charge Laid Against Brampton Man In The Death Of His Mother

    Advisory Remains: Tests On Saskatchewan City's Water Could Be Completed Tuesday

    Advisory Remains: Tests On Saskatchewan City's Water Could Be Completed Tuesday
    The Saskatchewan city of North Battleford says a precautionary drinking-water advisory remains in effect as officials wait for more test results.

    Advisory Remains: Tests On Saskatchewan City's Water Could Be Completed Tuesday

    Safeway Urges Consumers In Five Provinces To Throw Out Cooked Chicken Wings

    Safeway Urges Consumers In Five Provinces To Throw Out Cooked Chicken Wings
    Safeway is recalling several varieties of store-packaged, cooked chicken wings over concerns they may be contaminated with a toxin-producing bacteria.

    Safeway Urges Consumers In Five Provinces To Throw Out Cooked Chicken Wings

    Former KGB Worker Mikhail Lennikov Voluntarily Leaves Canada After 6 Years Avoiding Deportation

    Former KGB Worker Mikhail Lennikov Voluntarily Leaves Canada After 6 Years Avoiding Deportation
    VANCOUVER — A former KGB agent who spent six years living inside a Vancouver church to avoid deportation has voluntarily left Canada.

    Former KGB Worker Mikhail Lennikov Voluntarily Leaves Canada After 6 Years Avoiding Deportation

    Some B.C. Residents Can Relax As Crews Make Progress Corralling Two Wildfires

    Some B.C. Residents Can Relax As Crews Make Progress Corralling Two Wildfires
     Crews are making good progress on a pair of wildfires burning in the south Okanagan near Oliver, B.C., south of Penticton.

    Some B.C. Residents Can Relax As Crews Make Progress Corralling Two Wildfires