B.C. First Nations Lawyer Says Crown Didn't Consult On Specific Site C Permits

The Canadian Press, 19 Aug, 2015 10:30 AM
    VANCOUVER — Two northeastern British Columbia First Nations will suffer "irreparable harm" if thousands of hectares of old-growth forest are cleared to build the Site C dam, their lawyer says.
     
    John Gailus told B.C. Supreme Court that a stop-work order should be issued to halt the first phase of the nearly $9-billion hydroelectric project from proceeding along the Peace River.
     
    He said the Crown granted permits for the preparatory phase of construction without consulting with the West Moberly and Prophet River First Nations, which are members of the Treaty 8 Tribal Alliance.
     
    "The Crown truncated their consultation and issued the permits to meet an arbitrary timeline imposed by BC Hydro, we say, contrary to both its contractual obligations and its constitutional obligations," Gailus said Tuesday.
     
    The injunction application comes as the First Nations wait for both B.C. Supreme Court and Federal Court to deliver decisions on a judicial review aimed at quashing the hydroelectric project entirely.
     
    The provincial government granted approval in July for the first of seven construction phases, although the work hasn't yet started.
     
    Court heard the permits authorize the clearing of more than 1,600 hectares of forest, equivalent to about 4,500 truckloads of timber, along the south bank of the Peace River.
     
    Construction of new access roads and bridges, expansion of quarries and removal of beaver dams, eagle nests and the alteration of 163 archeological sites — which may include burial sites — was also authorized, Gailus said.
     
     
    He told court there's no urgency for starting the project.
     
    "There are significant benefits to the B.C. taxpayers for a delay," he said, adding costs will be higher if the work is allowed to move ahead and then the project is overturned.
     
    Outside court, West Moberly Chief Roland Willson called the consultation process a "farce."
     
    He said the First Nations signed an agreement in April to consult with the province on the first phase, but BC Hydro's permits were approved before any meetings.
     
    Willson was particularly concerned that up to 28 eagle nests would be destroyed.
     
    "It doesn't mean anything to anybody if we don't even talk about it and they approve (the permits)," he said. "We actually have to sit down and work through them together."
     
    Last month, Forests Minister Steve Thomson said each of the two dozen approved permit applications was reviewed for its potential impact on the environment and on aboriginal treaty rights.
     
    Thomson said the province conducted an "appropriate consultation process."
     
    BC Hydro expects construction of Site C to take at least a decade. The utility has said the project will power the equivalent of 450,000 homes per year.

    MORE National ARTICLES

    Third Day Of Deliberations At Inquest Examining Deadly Blast In Burns Lake, B.C.

    Third Day Of Deliberations At Inquest Examining Deadly Blast In Burns Lake, B.C.
    Forty-five-year-old Robert Luggi and 42-year-old Carl Charlie died in the Jan. 20, 2012 blast that seriously injured 19 others and destroyed Babine Forest Products near Burns Lake

    Third Day Of Deliberations At Inquest Examining Deadly Blast In Burns Lake, B.C.

    Wife Of Dead Officer Says RCMP Made Her Husband 'Scapegoat' In Robert Dziekanski Death

    The wife of an RCMP officer who killed himself two years ago claims that her husband was used by the Mounties a scapegoat in the death of Robert Dziekanski at Vancouver's airport in October 2007.

    Wife Of Dead Officer Says RCMP Made Her Husband 'Scapegoat' In Robert Dziekanski Death

    Jim Chu, Vancouver's Former Chief Constable Joins High Profile Private Sector Firm

    Chu has joined the Aquilini Investment Group (AIG) as vice president of special projects and partnerships.

    Jim Chu, Vancouver's Former Chief Constable Joins High Profile Private Sector Firm

    Report On Environmental Response To Vancouver Oil Spill Set To Be Released

    Report On Environmental Response To Vancouver Oil Spill Set To Be Released
    VANCOUVER — A report reviewing the coast guard's environmental response to a fuel spill in Vancouver's English Bay that soiled several beaches is expected to be released Friday.

    Report On Environmental Response To Vancouver Oil Spill Set To Be Released

    Long Delay Before Suspect In Murder Of Grandparents And Grandson Goes To Trial

    Long Delay Before Suspect In Murder Of Grandparents And Grandson Goes To Trial
    Douglas Garland was arrested last year following the disappearance of Alvin and Kathy Liknes and five-year-old Nathan O'Brien.

    Long Delay Before Suspect In Murder Of Grandparents And Grandson Goes To Trial

    Provincial Police Say Speeder Wanted To Reach Cottage In Time For Sunset

    Provincial Police Say Speeder Wanted To Reach Cottage In Time For Sunset
    Ontario Provincial Police say a car was clocked at 150 kilometres an hour in an 80 km/h zone earlier this week on the Bluewater Veteran's Highway near St. Joseph, on Lake Huron.

    Provincial Police Say Speeder Wanted To Reach Cottage In Time For Sunset