B.C. First Nations Lawyer Says Crown Didn't Consult On Specific Site C Permits

The Canadian Press, 19 Aug, 2015 10:30 AM
    VANCOUVER — Two northeastern British Columbia First Nations will suffer "irreparable harm" if thousands of hectares of old-growth forest are cleared to build the Site C dam, their lawyer says.
     
    John Gailus told B.C. Supreme Court that a stop-work order should be issued to halt the first phase of the nearly $9-billion hydroelectric project from proceeding along the Peace River.
     
    He said the Crown granted permits for the preparatory phase of construction without consulting with the West Moberly and Prophet River First Nations, which are members of the Treaty 8 Tribal Alliance.
     
    "The Crown truncated their consultation and issued the permits to meet an arbitrary timeline imposed by BC Hydro, we say, contrary to both its contractual obligations and its constitutional obligations," Gailus said Tuesday.
     
    The injunction application comes as the First Nations wait for both B.C. Supreme Court and Federal Court to deliver decisions on a judicial review aimed at quashing the hydroelectric project entirely.
     
    The provincial government granted approval in July for the first of seven construction phases, although the work hasn't yet started.
     
    Court heard the permits authorize the clearing of more than 1,600 hectares of forest, equivalent to about 4,500 truckloads of timber, along the south bank of the Peace River.
     
    Construction of new access roads and bridges, expansion of quarries and removal of beaver dams, eagle nests and the alteration of 163 archeological sites — which may include burial sites — was also authorized, Gailus said.
     
     
    He told court there's no urgency for starting the project.
     
    "There are significant benefits to the B.C. taxpayers for a delay," he said, adding costs will be higher if the work is allowed to move ahead and then the project is overturned.
     
    Outside court, West Moberly Chief Roland Willson called the consultation process a "farce."
     
    He said the First Nations signed an agreement in April to consult with the province on the first phase, but BC Hydro's permits were approved before any meetings.
     
    Willson was particularly concerned that up to 28 eagle nests would be destroyed.
     
    "It doesn't mean anything to anybody if we don't even talk about it and they approve (the permits)," he said. "We actually have to sit down and work through them together."
     
    Last month, Forests Minister Steve Thomson said each of the two dozen approved permit applications was reviewed for its potential impact on the environment and on aboriginal treaty rights.
     
    Thomson said the province conducted an "appropriate consultation process."
     
    BC Hydro expects construction of Site C to take at least a decade. The utility has said the project will power the equivalent of 450,000 homes per year.

    MORE National ARTICLES

    Alberta Needs To Strengthen Program To Deal With Dormant Oil Wells: Critics

    Alberta Needs To Strengthen Program To Deal With Dormant Oil Wells: Critics
     A program in Alberta to deal with thousands of dormant oil and gas wells that don't meet safety and monitoring standards needs to be strengthened, critics say as falling crude prices could see their numbers swell.

    Alberta Needs To Strengthen Program To Deal With Dormant Oil Wells: Critics

    Trial Dates To Be Set In November For Pair Accused Of Alleged Mall Shooting Plot

    Trial Dates To Be Set In November For Pair Accused Of Alleged Mall Shooting Plot
    HALIFAX — Two young people accused of plotting to shoot shoppers at a Halifax mall made a brief court appearance today for a pre-trial hearing.

    Trial Dates To Be Set In November For Pair Accused Of Alleged Mall Shooting Plot

    Activists Squealing About Quebec Pig Contest, Say It Abuses Animals

    Activists Squealing About Quebec Pig Contest, Say It Abuses Animals
    Animal-rights groups are squealing about an annual contest in a small Quebec town that features participants trying to grab greased pigs

    Activists Squealing About Quebec Pig Contest, Say It Abuses Animals

    Globe-Trotting HitchBot Returning To Canada For Possible Rebuild

    Globe-Trotting HitchBot Returning To Canada For Possible Rebuild
    The hitchhiking robot that became a social media darling as it documented its travels throughout the world likely hasn't taken its last ride, its co-creators said Wednesday.

    Globe-Trotting HitchBot Returning To Canada For Possible Rebuild

    MADD P.E.I. Chapter President Resigns After Impaired Driving Charges

    MADD P.E.I. Chapter President Resigns After Impaired Driving Charges
    The president of a Prince Edward Island chapter of Mothers Against Drunk Driving Canada has resigned after being charged with impaired driving, the organization's CEO said Wednesday.

    MADD P.E.I. Chapter President Resigns After Impaired Driving Charges

    Surrey Youth Soccer Club Suspended Over Allegations Of Financial Irregularities

    Surrey Youth Soccer Club Suspended Over Allegations Of Financial Irregularities
    Outgoing club head Garry Sangha says the move boils down to other clubs vying for access to the area's up-and-coming players and their registration dollars.

    Surrey Youth Soccer Club Suspended Over Allegations Of Financial Irregularities