Close X
Friday, November 29, 2024
ADVT 
National

B.C. First Nations Lawyer Says Crown Didn't Consult On Specific Site C Permits

The Canadian Press, 19 Aug, 2015 10:30 AM
    VANCOUVER — Two northeastern British Columbia First Nations will suffer "irreparable harm" if thousands of hectares of old-growth forest are cleared to build the Site C dam, their lawyer says.
     
    John Gailus told B.C. Supreme Court that a stop-work order should be issued to halt the first phase of the nearly $9-billion hydroelectric project from proceeding along the Peace River.
     
    He said the Crown granted permits for the preparatory phase of construction without consulting with the West Moberly and Prophet River First Nations, which are members of the Treaty 8 Tribal Alliance.
     
    "The Crown truncated their consultation and issued the permits to meet an arbitrary timeline imposed by BC Hydro, we say, contrary to both its contractual obligations and its constitutional obligations," Gailus said Tuesday.
     
    The injunction application comes as the First Nations wait for both B.C. Supreme Court and Federal Court to deliver decisions on a judicial review aimed at quashing the hydroelectric project entirely.
     
    The provincial government granted approval in July for the first of seven construction phases, although the work hasn't yet started.
     
    Court heard the permits authorize the clearing of more than 1,600 hectares of forest, equivalent to about 4,500 truckloads of timber, along the south bank of the Peace River.
     
    Construction of new access roads and bridges, expansion of quarries and removal of beaver dams, eagle nests and the alteration of 163 archeological sites — which may include burial sites — was also authorized, Gailus said.
     
     
    He told court there's no urgency for starting the project.
     
    "There are significant benefits to the B.C. taxpayers for a delay," he said, adding costs will be higher if the work is allowed to move ahead and then the project is overturned.
     
    Outside court, West Moberly Chief Roland Willson called the consultation process a "farce."
     
    He said the First Nations signed an agreement in April to consult with the province on the first phase, but BC Hydro's permits were approved before any meetings.
     
    Willson was particularly concerned that up to 28 eagle nests would be destroyed.
     
    "It doesn't mean anything to anybody if we don't even talk about it and they approve (the permits)," he said. "We actually have to sit down and work through them together."
     
    Last month, Forests Minister Steve Thomson said each of the two dozen approved permit applications was reviewed for its potential impact on the environment and on aboriginal treaty rights.
     
    Thomson said the province conducted an "appropriate consultation process."
     
    BC Hydro expects construction of Site C to take at least a decade. The utility has said the project will power the equivalent of 450,000 homes per year.

    MORE National ARTICLES

    Vancouver ESL Tutor, 70, Arrested For Sexual Interference Of 12-Year-Old Girl

    Vancouver ESL Tutor, 70, Arrested For Sexual Interference Of 12-Year-Old Girl
    Christopher Jon Adams was hired to tutor a girl after she arrived in Canada in 2013 and that an investigation began after allegations he may have touched the child for sexual purposes

    Vancouver ESL Tutor, 70, Arrested For Sexual Interference Of 12-Year-Old Girl

    Nurses Union, B.C. Government Invest Millions To Prevent Health-Care Assaults

    VANCOUVER — A string of assaults against health care workers has prompted the B.C. Nurses' Union and the provincial government to invest $2 million in violence prevention at four high-risk hospitals.

    Nurses Union, B.C. Government Invest Millions To Prevent Health-Care Assaults

    Montreal Cabbie Denied Bail After Allegedly Hitting Two Men With His Car

    Montreal Cabbie Denied Bail After Allegedly Hitting Two Men With His Car
    MONTREAL — A Montreal cabbie who allegedly struck two men on purpose with his vehicle has been denied bail.

    Montreal Cabbie Denied Bail After Allegedly Hitting Two Men With His Car

    Second Mass Stranding In 2 Days Sees All 14 Whales Helped Back To Sea

    Second Mass Stranding In 2 Days Sees All 14 Whales Helped Back To Sea
    BAYFIELD, N.S. — Another group of beached whales in Nova Scotia has been helped back out to sea, marking the second time this week that concerned residents joined together to save a stranded pod.

    Second Mass Stranding In 2 Days Sees All 14 Whales Helped Back To Sea

    The Choice In This Election Is Between Tories And The NDP, Says Tom Mulcair

    The Choice In This Election Is Between Tories And The NDP, Says Tom Mulcair
    The first televised debate will give voters an opportunity to see that the Oct. 19 election is about choice, New Democrat Leader Tom Mulcair

    The Choice In This Election Is Between Tories And The NDP, Says Tom Mulcair

    Judge Declares Dog Involved In Attack Dangerous And Must Be Euthanized

    Judge Declares Dog Involved In Attack Dangerous And Must Be Euthanized
    Two off-leash dogs attacked another dog in Peachland on Jan. 1, puncturing its lung.

    Judge Declares Dog Involved In Attack Dangerous And Must Be Euthanized