B.C. aware of dike problems before destructive flooding in 2021, documents show

Darpan News Desk The Canadian Press, 13 Sep, 2023 11:14 AM
  • B.C. aware of dike problems before destructive flooding in 2021, documents show

Officials with the British Columbia government and the City of Merritt were aware of significant problems with dikes for several years before a series of atmospheric rivers flooded the community, documents released through a freedom of information request show.

The documents obtained by the B.C. office of the Canadian Centre for Policy Alternatives show a registered professional engineer found numerous problems in 2018 with dikes protecting the community in the province's southern Interior. 

Dike maintenance is a municipal responsibility but with provincial oversight.

The engineer, Aaron Hahn with the B.C.-based consulting company Interior Dams, reiterated the same concerns in 2019, 2020 and in June 2021, just five months before the flooding that forced more than 7,000 people out of their homes.

Hahn's 2021 report identified ongoing concerns including "unauthorized excavations and modifications" to the city's dikes, as well as "excessive" vegetation growth, slumping and the loss of waterside embankment material, and the displacement of erosion protection measures such as rocks used for reinforcement.

The report would be Hahn's last before torrential rainfall pushed the Coldwater River to overflow its banks in November 2021, causing dike failures, the shutdown of the city's water system and wastewater treatment plant, as well as extensive property damage amounting to about $150 million, according to the city's website.

His 2019 checklist described large cottonwood trees and other vegetation as "rampant" along one of the dikes. Its integrity had been "severely compromised," wrote Hahn, classifying the problem as a "high priority" to be addressed within two years.

Hahn's 2021 checklist stated the crest of one of the dikes had been "severely eroded" or excavated in one area and identified a "possible sink hole."

The report, dated June 19, 2021, said "the dikes are in a similar condition to previous years with the exception of minor changes to erosion patterns and vegetation growth," suggesting no significant work had been done to address the problems.

Hahn's report recommended "immediate implementation" of maintenance and other activities to address the high-priority concerns.

Reached by phone, Hahn declined to comment further on his findings.

Ben Parfitt, who submitted the document request through his work as a resource policy analyst with the Canadian Centre for Policy Alternatives, said municipal authorities in B.C. are responsible for maintaining their own dikes.

But smaller communities often lack the funds necessary to make repairs, he said.

"The provincial government knows, or ought to know, that the costs of dealing with this infrastructure are in many cases beyond the ability of local government."

The Union of B.C. Municipalities endorsed a resolution in 2015 that called on the province to take back control of dikes managed by local governments, saying "the administrative and financial resources required to undertake these responsibilities are an increasingly unsustainable burden to small communities."

The union's website includes a response from the B.C. government at the time, which outlined its views on why the responsibility should stay with local authorities.

The union, which is the voice of local governments, endorsed a similar resolution in September 2022, saying the previous year's flooding had "emphasized the need to re-examine the province's 2003 decision to download diking responsibility to local governments."

While local authorities are responsible for dike maintenance, Parfitt noted the provincial inspector of dikes has powers under B.C.'s Dike Maintenance Act to inspect any dike and issue orders for necessary repairs or maintenance.

"They can issue orders at any point in time based either on inspections or their read of the (annual inspection reports) provided by the local dike authorities," he said.

If an order is not followed, the legislation stipulates the B.C. government may take steps to complete the work and recover its expenses from the local diking authority.

Yet Parfitt said the freedom of information request did not produce any such orders from the province in response to concerns about dikes in Merritt.

Parfitt had requested copies of annual dike inspection reports sent to the provincial inspector by authorities in Merritt, Abbotsford, Princeton, Chilliwack and Richmond between 2017 and 2021, as well as any related responses from the province.

The response to Parfitt's freedom of information request contains nearly 5,300 pages of documents, but he said just one page came from a source within the provincial government — an email pertaining to dikes in Princeton, B.C., about 90 kilometres south of Merritt, where a dike also failed during the 2021 flooding.

"If the flooding and other disasters that we saw in 2021 tell us anything, it is that governments should be spending money proactively to avert potentially bigger payouts down the road to fix things and to address other things, for example, lawsuits," he said, noting the B.C. government is named in lawsuits related to the flooding in Abbotsford and a landslide that killed five people that November.

The Ministry of Forests, which is responsible for overseeing dikes and dams in B.C., did not respond to a series of questions on dike oversight in time for publication.

Parfitt said he also sent questions to the ministry, and the answers he received did not provide a reason why provincial officials did not issue any orders for repair work to be carried out in response to Merritt's annual dike inspection reports.

Michael Goetz, who became mayor of Merritt a year after the severe flooding in November 2021, declined to be interviewed about the earlier dike inspections.

In an emailed statement, he said city officials are focused on moving forward with rebuilding and they would "possibly look back" once the community is secure.

A document posted by the city last year shows the B.C. government had provided just over $24 million for “interim flood support,” with nearly half earmarked for housing.

The city had also received approval for infrastructure repairs to be funded through the disaster financial assistance program, which sees costs split between the provincial and federal governments, the document said.

Last February, the province announced that it would provide Merritt with $2 million for diking around the city’s public works facility that had been inundated in 2021.

A flood mitigation study, funded with $329,000 from the province, has also been completed.

 

MORE National ARTICLES

Transit altercation results in a broken jaw and severed finger

Transit altercation results in a broken jaw and severed finger
On May 23rd just before 6:00 p.m., a physical altercation took place between two men, not known to each other, as they were boarding the same bus at the Marine Drive Canada Line Station in Vancouver. During the course of the altercation, a bus window was broken and a bystander was injured.  

Transit altercation results in a broken jaw and severed finger

B.C. staff who failed to check on two abused foster children lose jobs: ministry

B.C. staff who failed to check on two abused foster children lose jobs: ministry
While the Ministry of Children and Family Development did not provide the names or the number of people involved, it said in a statement "the staff who were directly involved in this case are no longer employed by the ministry." The statement said ministry staff did not follow its policy that children in care should be seen regularly by a social worker.    

B.C. staff who failed to check on two abused foster children lose jobs: ministry

7 infrastructure projects coming to BC

7 infrastructure projects coming to BC
A joint investment of more than 5.5-million-dollars will support work in Williams Lake, Prince George, Prince Rupert and Merritt. The projects involve improvements to the Cariboo Memorial Recreation Complex in Williams Lake as well as ventilation in four schools and a social housing complex in the northern region.

7 infrastructure projects coming to BC

Multiple boats stolen in Kelowna

Multiple boats stolen in Kelowna
Police are looking for witnesses after multiple boats were stolen from a locked campground in Kelowna. R-C-M-P say 14 boats were stolen between June 20th and 27th from McCurdy Place from within plain view of traffic on Highway 97.  

Multiple boats stolen in Kelowna

Searchers look for B.C. teen missing in provincial park since Tuesday

Searchers look for B.C. teen missing in provincial park since Tuesday
RCMP say 16-year-old Esther Wang from Langley, B.C., was part of a group of four people who were hiking in Golden Ears Provincial Park on Tuesday.  The group left a lookout point at about 2:45 p.m. to head back to their campground and about 15 minutes later they noticed that Wang was missing.

Searchers look for B.C. teen missing in provincial park since Tuesday

Sketch of an unidentified man released:VPD

Sketch of an unidentified man released:VPD
Vancouver Police have released a composite sketch of an unidentified man who died after being found in medical distress this spring. They say the man was found on the grounds of the Britannia Community Centre on March 24th and died later in hospital.  

Sketch of an unidentified man released:VPD