Officials with the British Columbia government and the City of Merritt were aware of significant problems with dikes for several years before a series of atmospheric rivers flooded the community, documents released through a freedom of information request show.

The documents obtained by the B.C. office of the Canadian Centre for Policy Alternatives show a registered professional engineer found numerous problems in 2018 with dikes protecting the community in the province's southern Interior. 

Dike maintenance is a municipal responsibility but with provincial oversight.

The engineer, Aaron Hahn with the B.C.-based consulting company Interior Dams, reiterated the same concerns in 2019, 2020 and in June 2021, just five months before the flooding that forced more than 7,000 people out of their homes.

Hahn's 2021 report identified ongoing concerns including "unauthorized excavations and modifications" to the city's dikes, as well as "excessive" vegetation growth, slumping and the loss of waterside embankment material, and the displacement of erosion protection measures such as rocks used for reinforcement.

The report would be Hahn's last before torrential rainfall pushed the Coldwater River to overflow its banks in November 2021, causing dike failures, the shutdown of the city's water system and wastewater treatment plant, as well as extensive property damage amounting to about $150 million, according to the city's website.

His 2019 checklist described large cottonwood trees and other vegetation as "rampant" along one of the dikes. Its integrity had been "severely compromised," wrote Hahn, classifying the problem as a "high priority" to be addressed within two years.

Hahn's 2021 checklist stated the crest of one of the dikes had been "severely eroded" or excavated in one area and identified a "possible sink hole."

The report, dated June 19, 2021, said "the dikes are in a similar condition to previous years with the exception of minor changes to erosion patterns and vegetation growth," suggesting no significant work had been done to address the problems.

Hahn's report recommended "immediate implementation" of maintenance and other activities to address the high-priority concerns.

Reached by phone, Hahn declined to comment further on his findings.

Ben Parfitt, who submitted the document request through his work as a resource policy analyst with the Canadian Centre for Policy Alternatives, said municipal authorities in B.C. are responsible for maintaining their own dikes.

But smaller communities often lack the funds necessary to make repairs, he said.

"The provincial government knows, or ought to know, that the costs of dealing with this infrastructure are in many cases beyond the ability of local government."

The Union of B.C. Municipalities endorsed a resolution in 2015 that called on the province to take back control of dikes managed by local governments, saying "the administrative and financial resources required to undertake these responsibilities are an increasingly unsustainable burden to small communities."

The union's website includes a response from the B.C. government at the time, which outlined its views on why the responsibility should stay with local authorities.

The union, which is the voice of local governments, endorsed a similar resolution in September 2022, saying the previous year's flooding had "emphasized the need to re-examine the province's 2003 decision to download diking responsibility to local governments."

While local authorities are responsible for dike maintenance, Parfitt noted the provincial inspector of dikes has powers under B.C.'s Dike Maintenance Act to inspect any dike and issue orders for necessary repairs or maintenance.

"They can issue orders at any point in time based either on inspections or their read of the (annual inspection reports) provided by the local dike authorities," he said.

If an order is not followed, the legislation stipulates the B.C. government may take steps to complete the work and recover its expenses from the local diking authority.

Yet Parfitt said the freedom of information request did not produce any such orders from the province in response to concerns about dikes in Merritt.

Parfitt had requested copies of annual dike inspection reports sent to the provincial inspector by authorities in Merritt, Abbotsford, Princeton, Chilliwack and Richmond between 2017 and 2021, as well as any related responses from the province.

The response to Parfitt's freedom of information request contains nearly 5,300 pages of documents, but he said just one page came from a source within the provincial government — an email pertaining to dikes in Princeton, B.C., about 90 kilometres south of Merritt, where a dike also failed during the 2021 flooding.

"If the flooding and other disasters that we saw in 2021 tell us anything, it is that governments should be spending money proactively to avert potentially bigger payouts down the road to fix things and to address other things, for example, lawsuits," he said, noting the B.C. government is named in lawsuits related to the flooding in Abbotsford and a landslide that killed five people that November.

The Ministry of Forests, which is responsible for overseeing dikes and dams in B.C., did not respond to a series of questions on dike oversight in time for publication.

Parfitt said he also sent questions to the ministry, and the answers he received did not provide a reason why provincial officials did not issue any orders for repair work to be carried out in response to Merritt's annual dike inspection reports.

Michael Goetz, who became mayor of Merritt a year after the severe flooding in November 2021, declined to be interviewed about the earlier dike inspections.

In an emailed statement, he said city officials are focused on moving forward with rebuilding and they would "possibly look back" once the community is secure.

A document posted by the city last year shows the B.C. government had provided just over $24 million for “interim flood support,” with nearly half earmarked for housing.

The city had also received approval for infrastructure repairs to be funded through the disaster financial assistance program, which sees costs split between the provincial and federal governments, the document said.

Last February, the province announced that it would provide Merritt with $2 million for diking around the city’s public works facility that had been inundated in 2021.

A flood mitigation study, funded with $329,000 from the province, has also been completed.

 

MORE National ARTICLES

Vancouver manslaughter conviction

Vancouver manslaughter conviction
Jeff Arnie Lincoln, 41, pleaded guilty to manslaughter and was sentenced on August 30th, following a Vancouver Police investigation that began more than two years earlier, when Lincoln assaulted 60-year-old Gilles Hebert in Grandview Park, near Commercial Drive and Charles Street. Hebert was taken to hospital and later died from his injuries.  

Vancouver manslaughter conviction

Prince George, B.C., explosion linked to pipe theft, gas buildup in structure: RCMP

Prince George, B.C., explosion linked to pipe theft, gas buildup in structure: RCMP
Police say the explosion that destroyed a building in downtown Prince George, B.C., last month was likely caused by "unauthorized" people who broke into the property and were unaware of a natural-gas buildup inside. Prince George RCMP say fire investigators have determined there is evidence of copper pipe theft, causing damage to at least one natural gas line. 

Prince George, B.C., explosion linked to pipe theft, gas buildup in structure: RCMP

Bank of Canada may need to raise rates again, despite this week's hold: Macklem

Bank of Canada may need to raise rates again, despite this week's hold: Macklem
The Bank of Canada may have to raise interest rates further, given that inflation may stay high for some time, said governor Tiff Macklem Thursday. His speech at the Calgary Chamber of Commerce came one day after the central bank decided to hold its key interest rate steady at five per cent as signs of an economic slowdown grow.

Bank of Canada may need to raise rates again, despite this week's hold: Macklem

Trudeau eyes Indo-Pacific trade deals to avoid China aim to 'play us off each other'

Trudeau eyes Indo-Pacific trade deals to avoid China aim to 'play us off each other'
Prime Minister Justin Trudeau says Canada's rocky relations with China have stabilized, while telling business leaders in Singapore that Ottawa has committed to a timeline for trade deals with the region. Trudeau is undertaking a weeklong visit to Indonesia, Singapore and India with a focus on shoring up trade in a region Ottawa sees as key to counteracting coercive economic moves by China. 

Trudeau eyes Indo-Pacific trade deals to avoid China aim to 'play us off each other'

Changes to minimum tax to add $2.6 billion over five years for feds: PBO

Changes to minimum tax to add $2.6 billion over five years for feds: PBO
The parliamentary budget officer says the federal government's proposed changes to the alternative minimum tax will generate an additional $2.6 billion in revenue over five years. The tax aims to ensure high-income earners and trusts don't pay disproportionately less in taxes than other taxpayers. 

Changes to minimum tax to add $2.6 billion over five years for feds: PBO

Federal prediction says parts of Canada could see wildfires through winter

Federal prediction says parts of Canada could see wildfires through winter
The latest federal government forecast says Canada's already unprecedented 2023 wildfire season could continue late into the fall or winter. Energy and Natural Resources Minister Jonathan Wilkinson says there is potential for increased wildland fire activity from eastern Alberta through to central Ontario at least until the end of this month, while fires in B.C. and the Northwest Territories will continue to smoulder.

Federal prediction says parts of Canada could see wildfires through winter