    VICTORIA — A chronology of events in British Columbia's Site C hydroelectric dam project:
     
    Late 1950s: The location for a third dam on the Peace River is first looked at after the locations of WAC Bennett Dam and Peace Canyon Dam were identified.
     
    1970s: Engineering work is done to determine the feasibility of a third dam.
     
    1989: Plans for Site C are shelved because of local opposition to the project. 
     
    March 2001: The chairman of BC Hydro says he would like to see the project revived and get fast-track approval from the government.
     
    April 2004: BC Hydro includes Site C in a package of initiatives it is studying to boost the province's long-term supply of hydroelectricity.
     
    December 2007: Preliminary cost estimates for Site C show the project could cost between $5 billion and $6.6 billion, doubling previous estimates by the province.
     
    April 2010: The B.C. government announces plan to build Site C.
     
    December 2013: Public hearings begin on the project.
     
    May 2014: A joint review panel gives no clear yes or no answer but says B.C. will need new energy at some point. It says the project would cause significant adverse effects on the environment and wildlife, as well as Aboriginal communities and farmers in the area.
     
    October 2014: Provincial and federal environmental certificates are issued. 
     
    December 2014: The B.C. government makes the decision to go ahead with construction.
     
    July 2015: Construction begins on Site C.
     
    July 2015: The B.C. Supreme Court dismissed a petition by the Peace Valley Landowner Association challenging provincial environmental approval of Site C. An appeal was dismissed in September 2016.
     
    August 2015: The federal court dismissed an application by Prophet River First Nation and West Moberly First Nations challenging environmental approval of Site C by the federal government. An appeal was dismissed in January 2017. 
     
    February 2016: A judge orders protesters to leave their tent camp near the construction site after BC Hydro seeks an injunction.
     
    December 2016: The government says the project is on schedule and on budget.
     
    March 2017: The government says more than 2,000 workers are employed at Site C.
     
    Aug. 2, 2017: The province's newly sworn-in NDP government asks the B.C. Utilities Commission to review the project as it considers cancelling or delaying its construction.
     
    Aug. 28, 2017: A United Nations panel says construction of the dam should be stopped until there is a full review of how it would affect Indigenous land.
     
    Nov. 1, 2017: The B.C. Utilities Commission says the project is over budget and behind schedule in its report to the government, which promises a decision on Site C's future by the end of the year.
     
    Dec. 11, 2017: Premier John Horgan says the dam will be completed but the price tag is expected to rise from $8.3 billion to $10.7 billion.

    MORE National ARTICLES

    Vancouver Fire Crews Responded To More Than 6,000 Overdose Calls This Year

    Vancouver Fire Crews Responded To More Than 6,000 Overdose Calls This Year
    Vancouver firefighters have responded to more than 6,000 overdose calls this year, a 28 per cent increase over last year with a month remaining in 2017.

    Vancouver Fire Crews Responded To More Than 6,000 Overdose Calls This Year

    He Was Going To Kill Me And Kill All Muslims, I Was Shocked: Noor Fadel

    He Was Going To Kill Me And Kill All Muslims, I Was Shocked: Noor Fadel
    I've experienced a lot of verbal assaults from people telling me to go back to my country but I haven't experienced anything to this extent

    He Was Going To Kill Me And Kill All Muslims, I Was Shocked: Noor Fadel

    Mountie Charged After Alleged Assault In Kamloops, B.C., Last August

    Mountie Charged After Alleged Assault In Kamloops, B.C., Last August
    VICTORIA — An RCMP officer has been charged with assault causing bodily harm in connection with an alleged incident in Kamloops, B.C.

    Mountie Charged After Alleged Assault In Kamloops, B.C., Last August

    Dog Makes Grim Discovery Of Human Foot In Shoe On Vancouver Island Beach

    Dog Makes Grim Discovery Of Human Foot In Shoe On Vancouver Island Beach
    SOOKE, B.C. — Another human foot has been found on British Columbia's coastline, the latest in more than a dozen such grim discoveries over the past decade.

    Dog Makes Grim Discovery Of Human Foot In Shoe On Vancouver Island Beach

    Specialist Wait Times Up In Canada, Says Study By Free-Enterprise Think Tank

    Specialist Wait Times Up In Canada, Says Study By Free-Enterprise Think Tank
    A new study says Canadians are waiting longer than ever for specialist treatment, but one health research organization says most patients are receiving key procedures within acceptable time frames.

    Specialist Wait Times Up In Canada, Says Study By Free-Enterprise Think Tank

    Aircraft-Type Bio-Vacuum Toilets On Indian Railways From January 2018

    Aircraft-Type Bio-Vacuum Toilets On Indian Railways From January 2018
    The first 100 coaches with the new toilets will be attached to important trains like Rajdhani and Shatabdi and would be rolled out from January 2018.

    Aircraft-Type Bio-Vacuum Toilets On Indian Railways From January 2018