    Late 1950s: The location for a third dam on the Peace River is first looked at after the locations of WAC Bennett Dam and Peace Canyon Dam were identified.
     
    1970s: Engineering work is done to determine the feasibility of a third dam.
     
    1989: Plans for Site C are shelved because of local opposition to the project. 
     
    March 2001: The chairman of BC Hydro says he would like to see the project revived and get fast-track approval from the government.
     
    April 2004: BC Hydro includes Site C in a package of initiatives it is studying to boost the province's long-term supply of hydroelectricity.
     
    December 2007: Preliminary cost estimates for Site C show the project could cost between $5 billion and $6.6 billion, doubling previous estimates by the province.
     
    April 2010: The B.C. government announces plan to build Site C.
     
    December 2013: Public hearings begin on the project.
     
    May 2014: A joint review panel gives no clear yes or no answer but says B.C. will need new energy at some point. It says the project would cause significant adverse effects on the environment and wildlife, as well as Aboriginal communities and farmers in the area.
     
    October 2014: Provincial and federal environmental certificates are issued. 
     
    December 2014: The B.C. government makes the decision to go ahead with construction.
     
    July 2015: Construction begins on Site C.
     
    July 2015: The B.C. Supreme Court dismissed a petition by the Peace Valley Landowner Association challenging provincial environmental approval of Site C. An appeal was dismissed in September 2016.
     
    August 2015: The federal court dismissed an application by Prophet River First Nation and West Moberly First Nations challenging environmental approval of Site C by the federal government. An appeal was dismissed in January 2017. 
     
    February 2016: A judge orders protesters to leave their tent camp near the construction site after BC Hydro seeks an injunction.
     
    December 2016: The government says the project is on schedule and on budget.
     
    March 2017: The government says more than 2,000 workers are employed at Site C.
     
    Aug. 2, 2017: The province's newly sworn-in NDP government asks the B.C. Utilities Commission to review the project as it considers cancelling or delaying its construction.
     
    Aug. 28, 2017: A United Nations panel says construction of the dam should be stopped until there is a full review of how it would affect Indigenous land.
     
    Nov. 1, 2017: The B.C. Utilities Commission says the project is over budget and behind schedule in its report to the government, which promises a decision on Site C's future by the end of the year.
     
    Dec. 11, 2017: Premier John Horgan says the dam will be completed but the price tag is expected to rise from $8.3 billion to $10.7 billion.

    MORE National ARTICLES

    Total number of Canadians impacted by cyber attack passes 19,000: Equifax Canada

    Total number of Canadians impacted by cyber attack passes 19,000: Equifax Canada
    11,670 of the affected credit cards are Canadian, bringing the total number of Canadians impacted by the hack to about 19,00

    Total number of Canadians impacted by cyber attack passes 19,000: Equifax Canada

    Liberal government launched Phoenix with 'no oversight' in place; Qualtrough

    Liberal government launched Phoenix with 'no oversight' in place; Qualtrough
    Public Services and Procurement Minister Carla Qualtrough made the prediction as she acknowledged there was no mechanism in place to gauge the effectiveness of Phoenix when the Liberals launched it early last year.

    Liberal government launched Phoenix with 'no oversight' in place; Qualtrough

    Canada 150 proved to be a big draw for tourism operators coast to coast

    Canada 150 proved to be a big draw for tourism operators coast to coast
    Destination Canada reported a 16 per cent increase in the number of Canadian millennials who vacationed within the country this year.

    Canada 150 proved to be a big draw for tourism operators coast to coast

    Federal marijuana legislation approved by Commons, moves on to Senate

    Federal marijuana legislation approved by Commons, moves on to Senate
    Some provinces have complained they can't be ready to implement and enforce the legislation so quickly.

    Federal marijuana legislation approved by Commons, moves on to Senate

    $100 million for gay purge victims as PM apologizes for LGBTQ discrimination

    $100 million for gay purge victims as PM apologizes for LGBTQ discrimination
    The money will be paid out as part of a class-action lawsuit settlement to employees who were investigated, sanctioned and sometimes fired as part of the so-called "gay purge."

    $100 million for gay purge victims as PM apologizes for LGBTQ discrimination

    Canadian rental vacancy rate decreases for the first time in three years: CMHC

    Canadian rental vacancy rate decreases for the first time in three years: CMHC
    The federal agency says the vacancy rate in Canadian cities with at least 10,000 people fell to three per cent in October, down from 3.7 per cent a year earlier.

    Canadian rental vacancy rate decreases for the first time in three years: CMHC