Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

One held at Madurai Airport with gold valued at Rs 96.18 lakh

One held at Madurai Airport with gold valued at Rs 96.18 lakh
The Customs officials have arrested a passenger at Madurai Airport and recovered 1,565 grams gold valued at Rs 96.18 lakh from him, officials said on Tuesday.  A senior Customs official said that the passenger was arrested following specific intelligence. The accused arrived at Madurai from Dubai.

One held at Madurai Airport with gold valued at Rs 96.18 lakh

Long queues, confusion in banks across Delhi as exchange of Rs 2,000 notes begins

Long queues, confusion in banks across Delhi as exchange of Rs 2,000 notes begins
Amar Singh, standing in a long queue at ICICI Bank branch in Green Park, said that there has been length of the line was there since the morning and chaos and confusion rules as bank staff are refusing to exchange the note and asking to deposit them.

Long queues, confusion in banks across Delhi as exchange of Rs 2,000 notes begins

Sisodia's letter from Tihar jail calls for education as key to equality, empowerment

Sisodia's letter from Tihar jail calls for education as key to equality, empowerment
Sisodia, through his letter which is written in Hindi, draws attention to the consequences of neglecting the education of the less fortunate, asserting that denying education to the impoverished not only perpetuates inequality but also fuels a vicious cycle of hatred and violence.

Sisodia's letter from Tihar jail calls for education as key to equality, empowerment

Aryan Khan case: SET report says NCB officials stole valuables of accused

Aryan Khan case: SET report says NCB officials stole valuables of accused
Sameer Wankhede, the former Mumabai zonal director of NCB, finds himself in a precarious position as allegations have emerged that he attempted to extort Rs 25 crore from Bollywood superstar Shah Rukh Khan in exchange of releasing his son Aryan Khan, who was accused in the Cordelia Cruise drugs case.

Aryan Khan case: SET report says NCB officials stole valuables of accused

Punjab Police conduct raids at premises of anti-social elements

Punjab Police conduct raids at premises of anti-social elements
Special DGP, Law and Order, Arpit Shukla said the day-long operation was conducted across the state in a synchronised manner and all the CPs and SSPs were asked to depute at least one police party per police station to check the whereabouts of these persons.

Punjab Police conduct raids at premises of anti-social elements

PM Modi arrives in Japan's Hiroshima to participate in G7 summit

PM Modi arrives in Japan's Hiroshima to participate in G7 summit
Modi on Friday embarked on a six-day visit to Japan, Papua New Guinea and Australia to attend three key multilateral summits, including that of the G7. He will also interact with Australian CEOs and business leaders, and meet the Indian community in Sydney at a special event.

PM Modi arrives in Japan's Hiroshima to participate in G7 summit