Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

No alliance when ideological differences exist, says Sidhu on AAP

No alliance when ideological differences exist, says Sidhu on AAP
Former Punjab Congress chief Navjot Singh Sidhu on Monday said that there cannot be an alliance where there are ideological differences, even as the Punjab leadership met party chief Mallikarjun Kharge here to discuss the support over ordinance to the AAP.  

No alliance when ideological differences exist, says Sidhu on AAP

UP districts fall short of immunisation targets

UP districts fall short of immunisation targets
The state health department has now decided to form district-level committees that shall work upon reasons for poor coverage and get the 'missed out' children vaccinated. Also, methods used by well-performing districts will be used elsewhere.

UP districts fall short of immunisation targets

Man dies after car falls from under-constructed Delhi flyover

Man dies after car falls from under-constructed Delhi flyover
The incident took place May 26 and the deceased was identified as Jagandeep, a resident of Krishna Nagar area. According to the police, information was received that a car had fallen from the flyover. 

Man dies after car falls from under-constructed Delhi flyover

Smartphone retrieval in India drains water reservoir

Smartphone retrieval in India drains water reservoir
A government official in India has been suspended from his job after he ordered a water reservoir to be drained so he could retrieve his smartphone, which he had dropped while taking a selfie. The smartphone was eventually retrieved but wouldn't even start because it was waterlogged.   

Smartphone retrieval in India drains water reservoir

Mumbai DRI makes bonfire of drugs worth around Rs 1,500 cr

Mumbai DRI makes bonfire of drugs worth around Rs 1,500 cr
The drugs that were reduced to ashes at the Mumbai Waste Management Ltd premises, included heroin (16.633 kg), cocaine (9.035 kg), methamphetamine (198.1 kg), marijuana (32.915 kg), mandrax tablets (81.91 kg) and MDMA tablets (134 gms), said an official.

Mumbai DRI makes bonfire of drugs worth around Rs 1,500 cr

Punjab Police bust gang involved in gang rivalry

Punjab Police bust gang involved in gang rivalry
The accused has been identified as Rahul, alias Akash, of Ferozepur. The police have also booked his close associate, Sukh, alias Subash.  Both are history-sheeters and have been facing criminal cases of crimes, including double murder, attempt to murder and possessing arms.

Punjab Police bust gang involved in gang rivalry