Close X
Thursday, September 19, 2024
ADVT 
India

Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

Sonia Gandhi on personal visit to Jaipur to avoid air pollution in Delhi: Jairam Ramesh

Sonia Gandhi on personal visit to Jaipur to avoid air pollution in Delhi: Jairam Ramesh
In a post on X, Congress General Secretary (Communication) Jairam Ramesh said, "Chairperson of Congress Parliamentary Party Smt. Sonia Gandhi is in Jaipur for the next few days to avoid the air pollution in New Delhi. It is a purely personal visit." He said that Rahul Gandhi will be based in Jaipur and campaign in Chhattisgarh on November 15 and in Rajasthan on November 16, 19, 21 and 22.

Sonia Gandhi on personal visit to Jaipur to avoid air pollution in Delhi: Jairam Ramesh

Delhi Police arrests two cyber fraudsters for cheating over 100 people

Delhi Police arrests two cyber fraudsters for cheating over 100 people
Delhi Police has arrested two cyber fraudsters for allegedly duping over 100 people on pretext of selling them iron road/TMT bars at cheaper rates after publishing advertisements on social media, an officer said on Friday. The accused were identified as Deepak Kumar (28) and Jitendra Kumar (32), both are residents of Bihar.

Delhi Police arrests two cyber fraudsters for cheating over 100 people

'Playing with fire': SC comes down heavily on Punjab Governor for withholding assent on bills

'Playing with fire': SC comes down heavily on Punjab Governor for withholding assent on bills
The Supreme Court on Friday came down heavily on the Punjab Governor for withholding assent to the bills passed by the state legislature. A bench, headed by CJI D.Y. Chandrachud, said that the Governor and the elected government being at loggerheads is a matter of "serious concern".  

'Playing with fire': SC comes down heavily on Punjab Governor for withholding assent on bills

Dhanteras sees strong demand for gold, silver ornaments; traders expect sales to surpass last year's level

Dhanteras sees strong demand for gold, silver ornaments; traders expect sales to surpass last year's level
The sale of gold and silver on the occasion of Dhanteras kickstarted on a positive note as the softening of precious metal's prices drew a good crowd to stores across the national capital. Recent falls in gold prices has given a confidence to the traders of surpassing the last year’s sales figures.

Dhanteras sees strong demand for gold, silver ornaments; traders expect sales to surpass last year's level

IT Dept seizes Rs 75 lakh in Jaipur’s Ganpati Plaza

IT Dept seizes Rs 75 lakh in Jaipur’s Ganpati Plaza
The IT Department on Friday again raided the Ganpati Plaza in Jaipur and seized Rs 75 lakh from one of its lockers. The IT Department recovered the cash from Royra Safety Wallets in Ganpati Plaza.

IT Dept seizes Rs 75 lakh in Jaipur’s Ganpati Plaza

Punjab CM implementing Centre’s agenda to end MSP on paddy: Harsimrat

Punjab CM implementing Centre’s agenda to end MSP on paddy: Harsimrat
Former Union minister Harsimrat Kaur Badal said on Friday that Punjab Chief Minister Bhagwant Mann is implementing Central government's agenda to end the minimum support price (MSP) regime on paddy by directing the state Advocate General to recommend it to the Supreme Court during a hearing on air pollution in Delhi.

Punjab CM implementing Centre’s agenda to end MSP on paddy: Harsimrat