Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

'Open US consulate in Chandigarh', Punjab Gov writes to EAM

'Open US consulate in Chandigarh', Punjab Gov writes to EAM
Punjab Governor Banwari Lal Purohit has written to the External Affairs Ministry (EAM) urging it to open a US Consulate in Chandigarh.  The Governor said the Punjabis are adventurous who travel all over the world. They also form a sizeable segment of the Indian diaspora in the US.

'Open US consulate in Chandigarh', Punjab Gov writes to EAM

Mob sets Central minister's house on fire in Imphal

Mob sets Central minister's house on fire in Imphal
According to police officials, a mob of 200 men and women attacked the Central Minister's residence late Thursday night. Singh, who is also the Minister of state for Education, is currently in Delhi. Though a portion of the minister's house got burnt, the security guards and firefighters managed to control the arson and saved most parts of the minister's house from being burnt down.

Mob sets Central minister's house on fire in Imphal

PM Modi to visit US, Egypt from June 20-25

PM Modi to visit US, Egypt from June 20-25
The visit will commence in New York, where Modi will lead the celebrations of the International Day of Yoga at the UN headquarters on June 21. In December 2014, the UN General Assembly had adopted a resolution proclaiming June 21 as the International Day of Yoga.

PM Modi to visit US, Egypt from June 20-25

Parents selling kids to child traffickers for Rs 500 in exchange of fake promises

Parents selling kids to child traffickers for Rs 500 in exchange of fake promises
Parents in different parts of the country, mostly from Bihar, are selling kids to child traffickers for Rs 500 in exchange of fake promises made by them who show them fancy dreams of their kids studying higher and earning well. 

Parents selling kids to child traffickers for Rs 500 in exchange of fake promises

Fake journalist, policemen held for extorting Rs 50,000 in Gurugram

Fake journalist, policemen held for extorting Rs 50,000 in Gurugram
A team of Gurugram police has arrested a gang of three people for allegedly extorting Rs 50,000 from a person, posing as a fake police officer and fake journalist, police said.  One of the gang members was arrested on June 6, and is identified as Sunil.

Fake journalist, policemen held for extorting Rs 50,000 in Gurugram

List of new Congress state secretaries revoked in Rajasthan

List of new Congress state secretaries revoked in Rajasthan
According to sources, the names of 85 Congress state secretaries were released on May 27, after the approval of the party's Rajasthan in-charge Sukhjinder Singh Randhawa. However, it has now been put on hold till further orders from the All India Congress Committee (AICC).

List of new Congress state secretaries revoked in Rajasthan