Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

Gurugram Police unearth Rs 55.86cr cyber crime fraud; 53 held

Gurugram Police unearth Rs 55.86cr cyber crime fraud; 53 held
The Gurugram Police have unearthed cyber fraud of around Rs 55.86 crore in the month of October and arrested 53 people in this connection, the police said on Wednesday. According to the police, 469 cyber fraud cases were registered against 53 suspects across India of which around 22 cases were registered with the Gurugram police.  

Gurugram Police unearth Rs 55.86cr cyber crime fraud; 53 held

We have failed children of Palestine: Priyanka Gandhi on Children's Day

We have failed children of Palestine: Priyanka Gandhi on Children's Day
Congress General Secretary Priyanka Gandhi, who has been critical of killings of the civilians and children in the Israel-Hamas war on the occasion of Children’s day again reiterated her demand to bring an end to the “horrendous violence” and said that we have “failed” the thousands of children that are being massacred in Palestine every moment. 

We have failed children of Palestine: Priyanka Gandhi on Children's Day

Tunnel collapse: Some trapped workers speak to their kin through pipe

Tunnel collapse: Some trapped workers speak to their kin through pipe
As rescue operations to save 40 labourers trapped in an under-construction tunnel in Uttarakhand's Uttarkashi district continued for the third day on Tuesday, the police facilitated their contact with their anxious kin through a pipe. Uttarkashi Police's CO Prashant Kumar, in a bid to bolster the trapped men's spirits, made arrangements for some of them to talk to their families through this mechanism.  

Tunnel collapse: Some trapped workers speak to their kin through pipe

Sahara Group founder Subrata Roy passes away at 75 after prolonged illness

Sahara Group founder Subrata Roy passes away at 75 after prolonged illness
'Saharasri' Subarata Roy, the founder of Sahara India Pariwar, breathed his last on Tuesday following a cardiac arrest after a prolonged illness. He was 75. Mourning the demise of Roy, the Sahara India Group said in a statement, "With profound sadness, the Sahara India Pariwar informs the demise of our ‘Saharasri’ Subrata Roy Sahara, Managing Worker and Chairman, Sahara India Pariwar.

Sahara Group founder Subrata Roy passes away at 75 after prolonged illness

13 people, including 10 kids, in Rajasthan lose eyesight due to firecracker accidents

13 people, including 10 kids, in Rajasthan lose eyesight due to firecracker accidents
A total of 13 people, including 10 children, across several cities of Rajasthan including Jaipur, Jhunjhunu, and Bharatpur lost sight in at least one eye while bursting firecrackers on Diwali, doctors said. This figure was reported after three days of surgery in the eye department of Sawai Mansingh (SMS) Hospital here, with the patients suffering damage to their cornea and retina.

13 people, including 10 kids, in Rajasthan lose eyesight due to firecracker accidents

Punjab: Passengers vandalise Sirhind Rly station over cancellation of Bihar-bound special train

Punjab: Passengers vandalise Sirhind Rly station over cancellation of Bihar-bound special train
According to Northern Railway officials, some angry passengers reportedly pelted stones after they came to know that the train which was supposed to leave for Katihar was cancelled. Meanwhile, Northern Railway CPRO Deepak Kumar said that connecting rake got delayed and the train was put back at 3 a.m. He said that regular announcements have been made at the railway station.  

Punjab: Passengers vandalise Sirhind Rly station over cancellation of Bihar-bound special train