Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

Sisodia's supporters, AAP activists barred from entering courtroom: Delhi court

Sisodia's supporters, AAP activists barred from entering courtroom: Delhi court
The judge's decision was prompted by an incident on June 1 when the senior AAP leader claimed that he was manhandled by security personnel during a court appearance. The lockup in-charge at Rouse Avenue Courts has also been directed to promptly report any violation of these instructions to the court.

Sisodia's supporters, AAP activists barred from entering courtroom: Delhi court

Fake call centre busted in Gurugram, four arrested

Fake call centre busted in Gurugram, four arrested
The call centre mostly used to cheat foreign nationals on the pretext of technical support, the police said on Thursday. According to the police, a team of the cyber crime police station led by ACP (Cyber Crime) Vipin Ahlawat, raided the call centre which was located at house no 135, Sector-47 in Gurugram following a tip-off.

Fake call centre busted in Gurugram, four arrested

Ex-Punjab CM Channi summoned third time in disproportionate assets case

Ex-Punjab CM Channi summoned third time in disproportionate assets case
The Vigilance Bureau has been probing the assets of Channi, his brothers, family members and some of his associates for amassing wealth more than their declared sources of income. Earlier, Channi appeared before the investigating agency on June 14 and he was questioned for over five hours.

Ex-Punjab CM Channi summoned third time in disproportionate assets case

Punjab CM closes 10th toll plaza in state

Punjab CM closes 10th toll plaza in state
Interacting with the media after closing the Singhawala toll plaza, the Chief Minister said people had to pay a hefty amount of Rs 44.43 while crossing these 10 toll plazas. However, he said with the closing of the 10 toll plazas people will be immensely benefited and get a major relief.  

Punjab CM closes 10th toll plaza in state

India, France may co-develop, co-produce combat aircraft engines

India, France may co-develop, co-produce combat aircraft engines
Prime Minister Narendra Modi will be visiting France on July 13 and he will take part in the Bastille Day Parade on July 14 as the Guest of Honour.He is expected to hold bilateral talks with President Macron on July 13. The Indian Air force’s Rafale fighter will be participating in the Bastille Day fly-past on July 14.

India, France may co-develop, co-produce combat aircraft engines

3 held at IGI with 6.5 kg gold worth over Rs 3 crore

3 held at IGI with 6.5 kg gold worth over Rs 3 crore
Customs officials at the Indira Gandhi International Airport here have arrested three passengers coming from Dubai for smuggling 6.5 kg gold worth Rs 3.28 crore, officials said on Wednesday. The customs officers said that all the three accused arrived at IGI from Dubai.

3 held at IGI with 6.5 kg gold worth over Rs 3 crore