Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

Delhi Police file FIR against man over call warning hijack of Air India flight

Delhi Police file FIR against man over call warning hijack of Air India flight
The Delhi Police on Sunday lodged an FIR against a man who made a call to the Air India call centre in Pune related to the "hijacking of Delhi-Tel Aviv flight". The call was made on July 13. The caller -- Anurag, a resident of Assam, claimed that he overheard that the flight was hijacked.

Delhi Police file FIR against man over call warning hijack of Air India flight

Traffic restored at some parts in Delhi as Yamuna flood waters recede

Traffic restored at some parts in Delhi as Yamuna flood waters recede
The Delhi Traffic Police on Monday said that several roads in the national capital, which were previously closed due to the overflow of the Yamuna River, have now been reopened. As flood waters are receding, normal traffic movement has been restored, bringing relief to commuters and residents in affected areas.

Traffic restored at some parts in Delhi as Yamuna flood waters recede

Pakistani supplier provided weapons to kill Moosewala, say NIA sources

Pakistani supplier provided weapons to kill Moosewala, say NIA sources
The Pakistani supplier has been identified as Hamid who currently lives in Dubai. The name came to the fore during the interrogation of a man, named Shahbaz Ansari, who was arrested by NIA in 2022. Moosewala, 29, was shot dead by gangsters close to his ancestral village in Mansa in broad daylight on May 29, 2022 in less than 24 hours after his security was curtailed by the Punjab government. 

Pakistani supplier provided weapons to kill Moosewala, say NIA sources

‘Opposition in Punjab dead’, says Akali Dal on Congress backing AAP

‘Opposition in Punjab dead’, says Akali Dal on Congress backing AAP
Saying the official Opposition in Punjab is dead, Shiromani Akali Dal leader Bikam Singh Majithia on Monday dubbed the AAP-Congress collusion as “an unholy wedlock” in which both parties have treated Punjab as a “bargaining dowry-chip to seal an immoral deal”. 

‘Opposition in Punjab dead’, says Akali Dal on Congress backing AAP

Punjab CM yet to announce ex-gratia for flood victims: Bajwa

Punjab CM yet to announce ex-gratia for flood victims: Bajwa
Congress leader Bajwa said it was quite evident now that the floods have wreaked havoc in 14 districts, severely damaging the farming sector and other occupations, including shopkeepers, small traders, and labourers. A considerable number of families in the flood-affected areas have got their houses damaged irreparably. 

Punjab CM yet to announce ex-gratia for flood victims: Bajwa

Indian students pursuing Masters in France to get 5-year work visa: PM Modi

Indian students pursuing Masters in France to get 5-year work visa: PM Modi
According to the latest official data collected post-Covid, there were around 6,000 Indian students in France in the 2021-2022 academic year. France plans to invite 20,000 Indian students in the country by the year 2025, Foreign Minister Catherine Colonna said last year.

Indian students pursuing Masters in France to get 5-year work visa: PM Modi