Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

Aircraft carrying Sonia, Rahul makes emergency landing in Bhopal

Aircraft carrying Sonia, Rahul makes emergency landing in Bhopal
The aircraft was forced to make the emergency landing due to inclement weather with heavy rains lashing Madhya Pradesh since Tuesday evening.  The Congress leaders were returning to Delhi from Bengaluru after attending the two-day brainstorming session of the opposition parties.

Aircraft carrying Sonia, Rahul makes emergency landing in Bhopal

Punjab hikes pension of freedom fighters

Punjab hikes pension of freedom fighters
Punjab Finance Minister Harpal Singh Cheema on Tuesday said the government has decided to increase the pension of freedom fighters from Rs 9,400 to Rs 11,000 per month. He said that this decision will be effective from August 1.

Punjab hikes pension of freedom fighters

India-US Strategic Clean Energy Partnership discuss future roadmap

India-US Strategic Clean Energy Partnership discuss future roadmap
The ministerial meeting of the SCEP, which was held between petroleum minister Hardeep Puri and US energy secretary Jennifer Granholm, appreciated deepened collaboration to scale and accelerate deployment of hydrogen technologies through the public-private hydrogen task force and other efforts in support of their national hydrogen strategies, including a focus on common cost reduction goals.

India-US Strategic Clean Energy Partnership discuss future roadmap

Mumbai police detect power theft of Rs 1.09 cr by plastic factory, owned booked

Mumbai police detect power theft of Rs 1.09 cr by plastic factory, owned booked
So far, Crohast Plastic Moulding Manufacturing Ltd has reportedly cheated Adani Electricity Ltd.  to the tune of around Rs 1.09 crore. The owner of the plastic factory, Pankaj Vasudevan Nair, has been booked under Section 135 of the Electricity Act, an official said.

Mumbai police detect power theft of Rs 1.09 cr by plastic factory, owned booked

ED files charge sheet against Revenue officials, 12 others in Punjab land grabbing case

ED files charge sheet against Revenue officials, 12 others in Punjab land grabbing case
The ED initiated a PMLA investigation based on an FIR registered by the Vigilance Bureau, Punjab under various sections of IPC and Prevention of Corruption Act. An ED official said that Dhoot was arrested by the ED on April 20 and is currently in judicial custody.  

ED files charge sheet against Revenue officials, 12 others in Punjab land grabbing case

CISF nabs 2 at IGI airport with gold valued at Rs 50L

CISF nabs 2 at IGI airport with gold valued at Rs 50L
Two persons were apprehended by the CISF personnel at the Indira Gandhi International Airport here for allegedly trying to smuggle in gold valued at Rs 50 lakh, an official said on Tuesday.  The accused have been identified as Khalid Maksud and Ranjeet Singh.

CISF nabs 2 at IGI airport with gold valued at Rs 50L