Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

Heavy rains in Himachal responsible for Punjab floods: Minister

Heavy rains in Himachal responsible for Punjab floods: Minister
Attributing heavy rains in Himachal Pradesh for floods in Punjab, state Water Resources Minister Gurmeet Singh Meet Hayer on Thursday held a review meeting with officials of the department to take stock of the flood situation in several districts and directed them to speed up the ongoing rescue and relief work.

Heavy rains in Himachal responsible for Punjab floods: Minister

Four accused held in Manipur women parade case, CM says will seek capital punishment

Four accused held in Manipur women parade case, CM says will seek capital punishment
Chief Minister N. Biren Singh, who had earlier said two more accused had been arrested, announced that maximum punishment would be accorded to the perpetrators. The CM, who also holds the home portfolio, said that interrogation of the two arrested persons is being conducted by the senior police officials and at this juncture, he would not be able to disclose the details.

Four accused held in Manipur women parade case, CM says will seek capital punishment

Punjab Police arrest Bishnoi gang member for making threat calls

Punjab Police arrest Bishnoi gang member for making threat calls
The arrested accused was identified as Kashmir Singh, alias Bobby Shooter (24), a resident of Patiala, who was working as a taxi driver. The police teams have also recovered a country-made pistol along with two cartridges with him.

Punjab Police arrest Bishnoi gang member for making threat calls

Punjab Police seize 13.7 lakh pharma opioids capsules, tablets

Punjab Police seize 13.7 lakh pharma opioids capsules, tablets
Punjab Director General of Police Gaurav Yadav on Wednesday said that it has busted one of biggest pharma opioids consignments by arresting two people and recovered 13.7 lakh capsules and tablets from their possession. The seizure by the Barnala police included tramadol capsules.  

Punjab Police seize 13.7 lakh pharma opioids capsules, tablets

Gurugram: Police seize 359 kg marijuana; 1 arrested

Gurugram: Police seize 359 kg marijuana; 1 arrested
The accused has been identified as Shabbir Khan (36), a resident of Nuh. The police also seized 359 kg of fine quality marijuana (ganja) from inside a truck. Based on the tip-off, the police reached the designated spot and apprehended the driver of a truck along and seized the large consignment of marijuana hidden inside it.  

Gurugram: Police seize 359 kg marijuana; 1 arrested

Delhi court directs officials to provide copy of CCTV clip to Sisodia on manhandling claim

Delhi court directs officials to provide copy of CCTV clip to Sisodia on manhandling claim
The lockup in-charge at Rouse Avenue Courts was also directed to promptly report any violation of these instructions to the court. During the hearing, the judge had informed the defence counsel that hybrid hearings are permissible and, with consent, the court could issue directions for Sisodia's appearance via video conference to prevent a recurrence of such incidents and ensure his safety.

Delhi court directs officials to provide copy of CCTV clip to Sisodia on manhandling claim