Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

Punjabi Bagh building collapse: Kejriwal govt announces Rs 20 lakh financial aid for victims’ family

Punjabi Bagh building collapse: Kejriwal govt announces Rs 20 lakh financial aid for victims’ family
Delhi Minister Atishi on Tuesday visited the Punjabi Bagh’s Arihant Nagar where two members of the caretaker’s family lost their lives. The Revenue Minister announced that the Delhi government will provide Rs 20 lakh as financial aid to the affected family.

Punjabi Bagh building collapse: Kejriwal govt announces Rs 20 lakh financial aid for victims’ family

‘Summoning special session patently illegal,’ Punjab Gov informs CM

‘Summoning special session patently illegal,’ Punjab Gov informs CM
The governor’s letter was in response to the Chief Minister’s assertion two days back that it is “very unfortunate” that the Governor “does not know whether the June 19-20 session was legal or illegal”. The Governor also warned the AAP government that he has been receiving complaints of corruption.  

‘Summoning special session patently illegal,’ Punjab Gov informs CM

3 Punjab museums to be closed for visitors till July 31 for maintenance work

3 Punjab museums to be closed for visitors till July 31 for maintenance work
The museums in Punjab -- Virasat-e-Khalsa in Anandpur Sahib, Dastan-e-Shahadat in Chamkaur Sahib, and the Golden Temple Plaza in Amritsar, under the Department of Tourism and Cultural Affairs -- will be closed for visitors till July 31 for half-yearly maintenance work.

3 Punjab museums to be closed for visitors till July 31 for maintenance work

Delhi’s infrastructure woes: Rs 1100 crore squandered amidst looming crisis

Delhi’s infrastructure woes: Rs 1100 crore squandered amidst looming crisis
Supreme Court’s latest remarks questioning the skewed priorities of the Delhi government have shed light on the mismanagement of funds and raised concerns over the condition of roads, garbage disposal, and infrastructure development in the national capital. The Delhi Government allocated Rs 65,000 crore in 2020-21; Rs 69,000 crore in 2021-22; and a staggering Rs 75,800 crore for 2022-23.

Delhi’s infrastructure woes: Rs 1100 crore squandered amidst looming crisis

Light of Life: Uplifting the Lives of underprivileged children  

Light of Life: Uplifting the Lives of underprivileged children  
Started in 2002 by Villy Doctor, this organization was founded to break the generational cycle of poverty – one life at a time. Since then, Villy has dedicated herself to transforming the lives of underprivileged rural communities, particularly women and children, empowering them to live with dignity and self-respect.   

Light of Life: Uplifting the Lives of underprivileged children  

Women paraded naked : Manipur court sends 4 accused to 11 days police custody

Women paraded naked : Manipur court sends 4 accused to 11 days police custody
A local court in Manipur’s Thoubal district on Friday sent the four accused arrested in connection with the parading of two naked women in Kangpokpi district on May 4, to police custody for 11 days to facilitate the police investigate the horrendous crime. 

Women paraded naked : Manipur court sends 4 accused to 11 days police custody