Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

Punjab to set up facilitation centre at Delhi airport for NRIs

Punjab to set up facilitation centre at Delhi airport for NRIs
In a landmark initiative aimed at facilitating the NRIs landing at the Indira Gandhi International Airport in New Delhi, the Punjab Cabinet led by Chief Minister Bhagwant Mann on Friday gave approval to set up a facilitation centre at the arrival hall of the international terminal.

Punjab to set up facilitation centre at Delhi airport for NRIs

'New UK visa rules deter foreign students from working till studies completed', Govt tells Parl

'New UK visa rules deter foreign students from working till studies completed', Govt tells Parl
The government on Friday told Parliament that as per new visa rules of the UK government, international students will not be able to switch out of the student route into work routes before their studies have been complete.  This became applicable from July 17, 2023 onwards, the government said, adding that the new visa rules will affect students from all nations. 

'New UK visa rules deter foreign students from working till studies completed', Govt tells Parl

Sahney urges PM Modi to reserve two seats for Kashmiri Sikhs

Sahney urges PM Modi to reserve two seats for Kashmiri Sikhs
The bill seeks to amend the Jammu and Kashmir Reorganization Act 2019 and reserve two seats for Kashmiri migrants and one seat for displaced people from Pakistan-occupied Kashmir (PoK) in the Union territory's legislative assembly.

Sahney urges PM Modi to reserve two seats for Kashmiri Sikhs

Badal welcomes Bathinda, Ludhiana being re-connected to Delhi via air

Badal welcomes Bathinda, Ludhiana being re-connected to Delhi via air
Shiromani Akali Dal (SAD) President Sukhbir Badal on Friday welcomed the Union government’s decision to connect Bathinda and Ludhiana to Delhi through a 19-seat aircraft under the Udan Regional Connectivity Scheme (RCS)

Badal welcomes Bathinda, Ludhiana being re-connected to Delhi via air

From being a fragile economy, India now among fastest growing economies: Sitharaman

From being a fragile economy, India now among fastest growing economies: Sitharaman
 Sitharaman observed that within nine years, the Indian economy has risen and experienced substantial economic growth, largely due to the government's policies, despite the Covid pandemic. She said that India finds itself in a unique situation of harbouring optimism and positivity regarding its future growth.

From being a fragile economy, India now among fastest growing economies: Sitharaman

Gurugram violence: Police crackdown continues, 79 arrested

Gurugram violence: Police crackdown continues, 79 arrested
While giving information about cases registered in Gurugram, Ramachandran said, "Police action is going on against those who spread violence. So far, 37 FIRs have been registered and 79 have been arrested by different teams of the Gurugram police.

Gurugram violence: Police crackdown continues, 79 arrested