Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

Assembly polls: BJP CEC identifies 125 'vulnerable seats' in MP, 22 in Chhattisgarh

Assembly polls: BJP CEC identifies 125 'vulnerable seats' in MP, 22 in Chhattisgarh
The seats on which the party has a higher chance to win or is in a fight have been placed under A and B categories. Whereas in the C and D categories, those seats have been included where the party has won the previous election with a very small margin or where it has never won an election. 

Assembly polls: BJP CEC identifies 125 'vulnerable seats' in MP, 22 in Chhattisgarh

Punjab Police arrest man who swam into Pak jurisdiction to retrieve narcotics

Punjab Police arrest man who swam into Pak jurisdiction to retrieve narcotics
The State Special Operation Cell (SSOC), Amritsar, had busted a cross-border drugs smuggling racket with the arrest of a drugs smuggler identified as Shinder Singh after recovering a consignment of 10 kg heroin and Rs 1.5 lakhs from his possession, while a woman drugs smuggler, Amandeep Kaur, alias Deep Bhai, linked to this module was also arrested with 1 kg heroin.

Punjab Police arrest man who swam into Pak jurisdiction to retrieve narcotics

Riding boat, Punjab CM visits flood-hit areas

Riding boat, Punjab CM visits flood-hit areas
Punjab Chief Minister Bhagwant Singh Mann on Thursday toured flood-affected areas in Hoshiarpur district in a boat to take stock of the situation. Boarding the boat with NDRF officials, the Chief Minister visited Rara and Fateh Kulla villages and then visited Haler village.

Riding boat, Punjab CM visits flood-hit areas

10 year-old suffers burn injuries on Delhi-Frankfurt flight

10 year-old suffers burn injuries on Delhi-Frankfurt flight
A young passenger, aged 10, who was on a Tata owned Vistara flight from Delhi to Frankfurt last week, suffered burn injuries due to a mishap involving a hot beverage spill. The child's family has criticised the airline for its inadequate response to the situation, asserting that the crew failed to apologise for the incident.  

10 year-old suffers burn injuries on Delhi-Frankfurt flight

8 held at IGI with 50 gold chains valued at around Rs 3cr

8 held at IGI with 50 gold chains valued at around Rs 3cr
Eight Uzbekistan nationals have been arrested at the Indira Gandhi International (IGI) Airport here allegedly trying to smuggle in 50 gold chains valued at around Rs 3 crore, an official said on Wednesday. A senior Customs official said that all the passengers were held on August 15, on the basis of passenger profiling.

8 held at IGI with 50 gold chains valued at around Rs 3cr

Register FIR against AAP legislator in assault case: Akali Dal leader

Register FIR against AAP legislator in assault case: Akali Dal leader
Majithia told the media here that “even though Sub-Inspector Kailash Chander was summoned by the legislator and beaten up when he was sitting in his office, an attempt is being made to dilute the case by registering an FIR against two AAP office-bearers”.

Register FIR against AAP legislator in assault case: Akali Dal leader