Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

India envoy to Canada says Ottawa has asked to 'take a pause' in trade talks

India envoy to Canada says Ottawa has asked to 'take a pause' in trade talks
India's envoy to Canada says Ottawa has tapped the brakes on trade negotiations, just before Prime Minister Justin Trudeau heads to New Delhi. Indian High Commissioner Sanjay Kumar Verma said Ottawa sought a pause "within the last month" to ongoing talks for an Early Progress Trade Agreement.

India envoy to Canada says Ottawa has asked to 'take a pause' in trade talks

G20 Summit: Over 100 'advanced' ambulances to remain on high alert for any medical emergency

G20 Summit: Over 100 'advanced' ambulances to remain on high alert for any medical emergency
The Health Minister said this while chairing a meeting of top officials of the Delhi Health Department, and senior officials of the various hospitals under it, to review the healthcare arrangements being made for the summit.

G20 Summit: Over 100 'advanced' ambulances to remain on high alert for any medical emergency

New Indo-US task force aims $100 bn electronics trade between 2 nations

New Indo-US task force aims $100 bn electronics trade between 2 nations
The India Cellular and Electronics Association (ICEA) organised the launch meeting here, attended by senior officials from Department of Telecommunications (DoT), US Embassy, leading US and Indian companies, investment banking fraternity, and Washington D.C.-headquartered Information Technology Industry Council (ITI).  India's electronics manufacturing industry is targeting $300 billion of electronics production by 2025-26.

New Indo-US task force aims $100 bn electronics trade between 2 nations

All smart city projects to be completed by June 2024, says Hardeep Puri

All smart city projects to be completed by June 2024, says Hardeep Puri
Union Minister for Housing and Urban Affairs Hardeep Singh Puri on Thursday said all smart city projects will be completed by June 2024. He also informed that all the projects are being monitored by the officials concerned.

All smart city projects to be completed by June 2024, says Hardeep Puri

Will withdraw decision to dissolve over 13,000 panchayats, Punjab informs HC

Will withdraw decision to dissolve over 13,000 panchayats, Punjab informs HC
Less than a fortnight after dissolving over 13,000 gram panchayats in Punjab, the government on Thursday informed the Punjab and Haryana High Court that it will withdraw the notification regarding the dissolution of gram panchayats in the state.

Will withdraw decision to dissolve over 13,000 panchayats, Punjab informs HC

ISI-backed terrorist Rinda’s six associates held in Punjab

ISI-backed terrorist Rinda’s six associates held in Punjab
The Punjab Police's Anti-Gangster Task Force (AGTF), in a joint operation with the Mohali police, arrested six associates of ISI-backed Pakistan-based terrorist Harwinder Singh, alias Rinda, and recovered five pistols along with ammunition from their possession, Director General of Police Gaurav Yadav said on Thursday. Those arrested have been identified as Roshan Kumar, Saurab Kumar, Vikram Kumar, Amrinder Singh, alias Billi, Arshveer Singh and Sunny, all residents of Patiala.

ISI-backed terrorist Rinda’s six associates held in Punjab