Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

Countdown for India’s rocket mission to the Sun begins at 12.20 pm

Countdown for India’s rocket mission to the Sun begins at 12.20 pm
Interestingly, India on August 23 reached the Moon with its lander safely landing on the lunar soil in a textbook style. Later the rover rolled down and started doing experiments. The Aditya-L1 -- named after the Sun God in Hindu mythology -- will be carried by the Indian rocket Polar Satellite Launch Vehicle-XL variant (PSLV-XL). On Saturday, the rocket will blast off at 11.50 a.m. from the Sriharikota rocket port in Andhra Pradesh, the ISRO said.

Countdown for India’s rocket mission to the Sun begins at 12.20 pm

Delhi Police arrests man on the run for last 12 years

Delhi Police arrests man on the run for last 12 years
A 45-year-old man evading arrest for the last 12 years was nabbed by police near Delhi’s Sarai Kale Khan area, an official said on Friday. The Deputy Commissioner of Police (South) Chandan Chowdhary said that on Wednesday a tip-off was received that a declared proclaimed offender would come at Surya Ghadi Park near Sarai Kale Khan.

Delhi Police arrests man on the run for last 12 years

Air India has recruited more than 650 pilots since April 1, says CEO Campbell Wilson

Air India has recruited more than 650 pilots since April 1, says CEO Campbell Wilson
The Air India group has successfully hired and brought on board a total of 650 pilots since April this year, Air India CEO Campbell Wilson said in his Friday message. His message comes days after the Directorate General of Civil Aviation (DGCA) had suspended simulators training for A320 pilots at Air India's Hyderabad facility and Boeing pilots at the Tata Group-owned airline's Mumbai facility.

Air India has recruited more than 650 pilots since April 1, says CEO Campbell Wilson

Punjab CM dissolved 13,000 panchayats eyeing to usurp Rs 1,000 crore: Sukhbir Badal

Punjab CM dissolved 13,000 panchayats eyeing to usurp Rs 1,000 crore: Sukhbir Badal
Eyeing to usurp Rs 1,000 crore of Panchayati Raj funds, Punjab Chief Minister Bhagwant Mann and Panchayati Raj Minister Laljit Bhullar were responsible for dissolving panchayats six months before the term, Shiromani Akali Dal (SAD) President Sukhbir Badal said on Friday.

Punjab CM dissolved 13,000 panchayats eyeing to usurp Rs 1,000 crore: Sukhbir Badal

Man arrested for hoax call about terror attack at Mumbai's Hotel Taj

Man arrested for hoax call about terror attack at Mumbai's Hotel Taj
Mumbai, Sep 1 (IANS) A 36-year-old man has been arrested here on Friday for allegedly making a false call claiming a "terror attack" on the renowned Hotel Taj, the police said. The arrested individual has been identified as Jagdamba Prasad Singh.

Man arrested for hoax call about terror attack at Mumbai's Hotel Taj

PM Modi congratulates RBI Governor for receiving A+ rating in Global Finance Central Banker Report Cards 2023

PM Modi congratulates RBI Governor for receiving A+ rating in Global Finance Central Banker Report Cards 2023
The Central Banker Report Cards, published annually by Global Finance since 1994, grade the central bank governors of 101 key countries, territories and districts, including the European Union, the Eastern Caribbean Central Bank, the Bank of Central African States and the Central Bank of West African States.

PM Modi congratulates RBI Governor for receiving A+ rating in Global Finance Central Banker Report Cards 2023