Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

Take steps to ensure resolution of dispute with Canada soon: Sukhbir Badal

Take steps to ensure resolution of dispute with Canada soon: Sukhbir Badal
Briefing the Home Minister in his office during a meeting in Parliament, the SAD president informed Shah that he was receiving distress calls from Punjabis in Canada who were worried about safe and smooth travel facilities to their homeland. He said similarly students were apprehensive about their future.

Take steps to ensure resolution of dispute with Canada soon: Sukhbir Badal

India suspends visa services for citizens of Canada, tells it to cut its diplomats

India suspends visa services for citizens of Canada, tells it to cut its diplomats
"Important notice from Indian Mission: Due to operational reasons, with effect from 21 Sept. Indian visa services have been suspended till further notice,” the BLS Indian Visa Application Center in Canada said. It gave no further details. BLS is the agency that processes visa requests for India.

India suspends visa services for citizens of Canada, tells it to cut its diplomats

Jaishankar briefs PM Modi on Canada issue: Sources

Jaishankar briefs PM Modi on Canada issue: Sources
Amid diplomatic standoff between India and Canada over the killing of Khalistani terrorist Hardeep Singh Nijjar, External Affairs Minister S. Jaishankar is learnt to have briefed Prime Minister Narendra Modi on the developments. According to sources, Jaishankar met the Prime Minister in Parliament and is learnt to have briefed him over the developments related to Canada, sources said.

Jaishankar briefs PM Modi on Canada issue: Sources

Tikait warns of agitation if demands are not met

Tikait warns of agitation if demands are not met
Bhartiya Kisan Union (BKU) leader Rakesh Tikait has said that the farmers will be forced to step up their agitation against the government if their demands, including free electricity for irrigation and higher SAP for sugarcane, were not met. Tikait told reporters that the recent agitation of farmers in Lucknow was not driven by any political agenda in view of the Lok Sabha elections due next year.

Tikait warns of agitation if demands are not met

Nari Shakti Vandan Adhiniyam a historic legislation, will further boost women empowerment: PM Modi

Nari Shakti Vandan Adhiniyam a historic legislation, will further boost women empowerment: PM Modi
Prime Minister Narendra Modi on Wednesday thanked MPs across party lines as the Lok Sabha passed the Women’s Reservation Bill, saying that it is a historic legislation that will further boost women empowerment and will enable greater participation of women in the political process.  

Nari Shakti Vandan Adhiniyam a historic legislation, will further boost women empowerment: PM Modi

PM suggests naming old Parliament building Samvidhan Sadan as MPs move to new building

PM suggests naming old Parliament building Samvidhan Sadan as MPs move to new building
Addressing a function in Central Hall to commemorate the 75 years of Parliament, Modi said, "I have a suggestion. Now, when we are going to the new Parliament, the dignity of the old building should never go down. This should not be left just as the old Parliament building. So, I urge that if you agree, this should be known as 'Samvidhan Sadan'."

PM suggests naming old Parliament building Samvidhan Sadan as MPs move to new building