Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

Sukhbir Badal asks Punjab CM to give financial aid to farmers for managing paddy stubble

Sukhbir Badal asks Punjab CM to give financial aid to farmers for managing paddy stubble
Asserting that it was high time that the AAP government in Punjab is held accountable, Badal called for an audit of all infrastructure projects which were on a standstill because the state was not releasing funds for them.  

Sukhbir Badal asks Punjab CM to give financial aid to farmers for managing paddy stubble

UP govt chopper lands in ground during sports event in school

UP govt chopper lands in ground during sports event in school
Screens, flags, canopies and marquees installed for the 139th Junior School Sports Day event were uprooted, parent of one of the children said. "A potential disaster was averted. Swirling dust momentarily blinded around 200 children on the ground," the parent said.  

UP govt chopper lands in ground during sports event in school

CBI busts cyber-crime module; seizes Rs 2.2cr 

CBI busts cyber-crime module; seizes Rs 2.2cr 
The Central Bureau of Investigation (CBI) on Wednesday said that it busted a major module of cyber enabled crimes allegedly coercing foreign nationals for payments, adding it also carried out searches around 24 locations across multiple states in this connection which led to recovery of cash of Rs 2.2 crore.

CBI busts cyber-crime module; seizes Rs 2.2cr 

India deports 7 Bangladeshi nationals through Assam border

India deports 7 Bangladeshi nationals through Assam border
At least seven Bangladeshi nationals, including three minors and two women, were deported back to their country through the India-Bangladesh international border at Assam's Karimganj district, officials said. All of them entered India from a location close to Agartala in Tripura, according to officials with the Border Security Force (BSF), and they were detained in Assam while on the way to Delhi.

India deports 7 Bangladeshi nationals through Assam border

Delhi Hospital Horror: 'Fake' doctors were performing operations on 'outdated' table, reveals probe

Delhi Hospital Horror: 'Fake' doctors were performing operations on 'outdated' table, reveals probe
Investigators have made shocking revelations about the south Delhi-based Agarwal Medical Centre, where surgeries were allegedly being performed without any valid permission by fake doctors. Deputy Commissioner of Police (South) Chandan Chowdhary told IANS that the operation table being used in the hospital was "second hand and outdated".

Delhi Hospital Horror: 'Fake' doctors were performing operations on 'outdated' table, reveals probe

Fake call centre busted in Gurugram; 12 including owner held

Fake call centre busted in Gurugram; 12 including owner held
The cyber crime team of Gurugram Police busted an illegal call centre operating in a house in the residential area of ​DLF Phase-3 in Gurugram. The call centre mostly used to cheat foreign nationals on the pretext of technical assistance, the police said. While duping their clients, they used to introduce themselves as a service provider of Apple, Microsoft, Amazon, Paypal, etc.

Fake call centre busted in Gurugram; 12 including owner held