Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

Meta purged over 19 mn bad pieces of content on FB, Insta in India in August

Meta purged over 19 mn bad pieces of content on FB, Insta in India in August
Meta said that it took down over 14 million pieces of content across 13 policies for Facebook and over five million pieces of content across 12 policies for Instagram in India in August. Between August 1-31, Facebook received 25,049 reports through the Indian grievance mechanism, and said that it provided tools for users to resolve their issues in 2,701 cases.  

Meta purged over 19 mn bad pieces of content on FB, Insta in India in August

India’s first woman astronaut Kalpana Chawla’s father passes away at 90

India’s first woman astronaut Kalpana Chawla’s father passes away at 90
 India’s first woman astronaut late Kalpana Chawla’s father Banarasi Lal Chawla passed away at a private hospital in Haryana’s Karnal on Tuesday. He was 90. Chawla was undergoing treatment for the past few days. His body will be donated to the Kalpana Chawla Medical College in Karana, said the family.

India’s first woman astronaut Kalpana Chawla’s father passes away at 90

Punjab CM furnishes every single penny detail to Governor

Punjab CM furnishes every single penny detail to Governor
Citing financial prudence and optimum utilisation of state resources, Punjab Chief Minister Bhagwant Mann on Tuesday furnished complete details of every single penny spent by the government in past 18 months to Governor Banwarilal Purohit. In a letter to the Governor, Mann apprised that Rs 27,016 crore has been paid by state as payment of interest whereas Rs 10,208 crore have been utilised as capital expenditure.

Punjab CM furnishes every single penny detail to Governor

24, including 12 infants, die in 24 hours at Nanded hospital; MVA slams govt

24, including 12 infants, die in 24 hours at Nanded hospital; MVA slams govt
According to officials, among the dead are at least 12 infants aged between 2 and 4 days, while the remaining are adults in some cases of ‘poisoning’ at the Dr. Shankarrao Chavan Government Medical College & Hospital.

24, including 12 infants, die in 24 hours at Nanded hospital; MVA slams govt

Sukhbir questions Kejriwal on Rs 50,000 crore investments in Punjab

Sukhbir questions Kejriwal on Rs 50,000 crore investments in Punjab
Reacting to Kejriwal’s statement that Punjab had received an investment of Rs 50,000 crore, the SAD chief said Kejriwal should substantiate this claim or apologise to Punjabis for lying to them. He said that forget attracting any investment, Punjab has witnessed a flight of industry to Uttar Pradesh as well as other states during AAP's tenure.

Sukhbir questions Kejriwal on Rs 50,000 crore investments in Punjab

12 state-of-the-art libraries opened in Punjab, 16 more to come up

12 state-of-the-art libraries opened in Punjab, 16 more to come up
In an initiative aimed at inculcating reading habits among the youth, Punjab Chief Minister Bhagwant Mann on Friday dedicated 12 state-of-the-art libraries. "These 12 libraries are just a beginning and 16 more such libraries will be soon inaugurated," the Chief Minister said while addressing the gathering here.   

12 state-of-the-art libraries opened in Punjab, 16 more to come up