Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

Delhi Police arrest editor of NewsClick; seize phones, laptops of journos

Delhi Police arrest editor of NewsClick; seize phones, laptops of journos
Police in New Delhi, India have arrested the editor of a news website and its human resources chief after raiding the homes of journalists working for the site and seizing their laptops and cellphones. NewsClick has been critical of Prime Minister Narendra Modi and his Hindu nationalist-led government.

Delhi Police arrest editor of NewsClick; seize phones, laptops of journos

Empowering Change: The Impactful Journey of CARE India in 70 Years

Empowering Change: The Impactful Journey of CARE India in 70 Years
CARE India, an affiliate of the global CARE network, is a leading humanitarian and development organization operational in India for over 70 years. The organization envisions a world where everyone can exercise their rights and live a life of dignity. 

Empowering Change: The Impactful Journey of CARE India in 70 Years

India needs to increase solar capacity by 36% every year: Ember

India needs to increase solar capacity by 36% every year: Ember
India needs to increase annual solar capacity additions by 36 per cent every year to meet its 2027 target, a new analysis by global energy think tank Ember said on Tuesday. Solar and wind could drive two-third of power generation growth by 2032 if India is on track to deliver its electricity plan, based on its analysis. 

India needs to increase solar capacity by 36% every year: Ember

Delhi Police raid over 30 locations linked to NewsClick; seize phones, laptops of journos

Delhi Police raid over 30 locations linked to NewsClick; seize phones, laptops of journos
Delhi Police’s Special Cell on Tuesday raided more than 30 locations in the national capital which included the premises of NewsClick, as well as the residences of its journalists, after the media outlet was accused of receiving funds from China. However, no arrests have been made so far.  

Delhi Police raid over 30 locations linked to NewsClick; seize phones, laptops of journos

Delhi excise policy case: SC to hear Manish Sisodia's bail plea on Wednesday

Delhi excise policy case: SC to hear Manish Sisodia's bail plea on Wednesday
The apex court adjourned the bail plea hearing after a joint request by lawyers from both sides on September 15. Sisodia has two special leave petitions listed for Wednesday against the Central Bureau of Investigation (CBI) and Enforcement Directorate (ED). He is facing a money laundering probe in connection with the alleged Delhi excise policy scam.

Delhi excise policy case: SC to hear Manish Sisodia's bail plea on Wednesday

Two prime suspects in Rs 18 crore crypto fraud case in Himachal arrested

Two prime suspects in Rs 18 crore crypto fraud case in Himachal arrested
Two prime accused in the crypto currency fraud of approximate Rs 18 crore have been arrested by the Special Investigating Team of Himachal Pradesh Police, officials investigating the scam said on Tuesday. The SIT headed by Deputy Inspector General (DIG) Abhishek Dullar comprising 13 members was constituted on September 26 to investigate cases related to crypto currency.

Two prime suspects in Rs 18 crore crypto fraud case in Himachal arrested