Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

'Need to deal with compassion': SC asks Centre to decide on Rajoana's mercy plea in 2 months

'Need to deal with compassion': SC asks Centre to decide on Rajoana's mercy plea in 2 months
The Ministry of Home Affairs (MHA) has also argued that the mercy petition cannot be decided until the appeals filed by other convicts in the case before the apex court are not disposed of. Also, Rajoana has not challenged his conviction or sentence, either before the high court or the Supreme Court

'Need to deal with compassion': SC asks Centre to decide on Rajoana's mercy plea in 2 months

5th arrest by NCB in Shaheen Bagh drug haul case, Dubai hawala link found

5th arrest by NCB in Shaheen Bagh drug haul case, Dubai hawala link found
Earlier, four persons, including two Afghanistan nationals, were arrested by the NCB. The fifth accused Shamim Ahmad was arrested from from Laxmi Nagar. A person called Shahid controlled the hawala racket of Dubai. Seeing that Shamim had good links with middlemen working in Dubai, Shahid included him in his gang.

5th arrest by NCB in Shaheen Bagh drug haul case, Dubai hawala link found

Punjab to begin delivery of ration at doorsteps

Punjab to begin delivery of ration at doorsteps
Conceding the proposal of the Food, Civil Supplies and Consumer Affairs Department to introduce home delivery of atta under National Food Security Act (NFSA), the entire state has been divided into eight zones and the service will commence in one zone in the first phase, in two zones in the second phase, and in the remaining five zones in the last and third phase.

Punjab to begin delivery of ration at doorsteps

Punjab okays recruitment to 26,454 posts in govt departments

Punjab okays recruitment to 26,454 posts in govt departments
A decision to this effect was taken during a cabinet meeting chaired by Chief Minister Bhagwant Mann. A spokesperson for the Chief Minister's Office said the posts belong to Group A, B and C. Major departments include Home Affairs, School Education, Health, Power and Technical Education.

Punjab okays recruitment to 26,454 posts in govt departments

Will strive to make education more inclusive, equitable: AAP Punjab MP

Will strive to make education more inclusive, equitable: AAP Punjab MP
Besides Mittal, the Chancellor of Lovely Professional University (LPU), others who were elected in the recently concluded biennial election from Punjab are businessman Sanjeev Arora and AAP Punjab co in-charge Raghav Chadha.

Will strive to make education more inclusive, equitable: AAP Punjab MP

Cocaine valued at Rs 80 crore seized in Hyderabad

Cocaine valued at Rs 80 crore seized in Hyderabad
In April, 1.15 kg of cocaine concealed in pills ingested by a passenger was seized at Hyderabad, and in another case one kg of cocaine was seized at Bengaluru in August 2021. Apart from Mumbai and Hyderabad, seizures of cocaine have also been affected at other airports also.

Cocaine valued at Rs 80 crore seized in Hyderabad