New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

Youth Cong takes out peace march to pay tribute to Moosewala

Youth Cong takes out peace march to pay tribute to Moosewala
Youth Congress national president Srinivas BV said that within a span of a few months, the AAP government has shown Punjab everything which was unimaginable.

Youth Cong takes out peace march to pay tribute to Moosewala

Special Cell gets 5-day remand of Lawrence Bishnoi in Moosewala case

Special Cell gets 5-day remand of Lawrence Bishnoi in Moosewala case
Earlier in the day Bishnoi had alleged that the Punjab police can do mishappening with him under political pressure. His plea has been accepted by the Delhi High Court which will hear arguments in the matter. Moosewala's autopsy revealed that he had 24 bullet injuries whereas 30 rounds were fired.

Special Cell gets 5-day remand of Lawrence Bishnoi in Moosewala case

First person arrested in Moosewala killing sent to 5-day police custody

First person arrested in Moosewala killing sent to 5-day police custody
A team of Punjab Police along with sleuths of the Uttarakhand STF had arrested Manpreet Singh from Dehradun on Monday. He was suspected to have provided "key logistical support" in the murder of the Punjabi singer.

First person arrested in Moosewala killing sent to 5-day police custody

Russian assault rifle AN-94 used by assassins of Moosewala?

Russian assault rifle AN-94 used by assassins of Moosewala?
It is learnt that the AK-47 assault rifle was used in the crime as its bullet shells were recovered from the crime scene.  The Punjab police is not leaving any stone unturned in its probe in the matter.

Russian assault rifle AN-94 used by assassins of Moosewala?

Punjab CM orders probe by sitting HC judge into Moosewala killing

Punjab CM orders probe by sitting HC judge into Moosewala killing
The Chief Minister, while acceding to the request of Balkar Singh Sidhu, the father of slain singer, said the state government will be requesting the Chief Justice of the High Court to get the case enquired into by a sitting judge.

Punjab CM orders probe by sitting HC judge into Moosewala killing

Samyukt Kisan Morcha demands judicial probe into attack on Rakesh Tikait

Samyukt Kisan Morcha demands judicial probe into attack on Rakesh Tikait
Bharatiya Kisan Union leader Tikait was attacked with black paint during a press conference at Bengaluru on 'Raita Chaluvali, Aatmavalokana haagu Spasteekarana Sabha (Farmer's Movement, Introspection and Clarification Meeting)' organised by Karnataka State Farmers Association, affiliated to the SKM, and Hasiru Sene.

Samyukt Kisan Morcha demands judicial probe into attack on Rakesh Tikait