Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

Connect with media to be strengthened: Punjab minister Arora

Connect with media to be strengthened: Punjab minister Arora
Arora, who has been elected for the second consecutive time as the MLA from Sunam, expressed gratitude towards the party national convenor and Delhi Chief Minister Arvind Kejriwal and Punjab Chief Minister Bhagwant Singh Mann and assured that he would discharge the responsibility assigned to him with honesty and dedication.

Connect with media to be strengthened: Punjab minister Arora

Man returning home with family shot dead in Delhi

Man returning home with family shot dead in Delhi
The motive behind the murder was not yet clear, according to the police. Police said, the man went to a local market for shopping along with his family. He was shot dead when he was on his way back home.

Man returning home with family shot dead in Delhi

Punjab CM to tie the knot for second time on Thursday

Punjab CM to tie the knot for second time on Thursday
In his previous marriage to Inderpreet Kaur, which ended in a divorce in 2016, Mann has two children -- son Dilshan and daughter Seerat -- who are currently staying in the US with their mother. Both children had attended Mann's swearing-in ceremony at Khatkar Kalan on March 16.

Punjab CM to tie the knot for second time on Thursday

Punjab to provide 600 units of free power to every household per billing cycle

Punjab to provide 600 units of free power to every household per billing cycle
A spokesman for the Chief Minister's office said all domestic consumers in the state would be eligible to get zero bills if their consumption is up to 600 units in every billing cycle.  This will give a big reprieve to the domestic consumers who have to hitherto shell out huge money every month in the form of power tariff.

Punjab to provide 600 units of free power to every household per billing cycle

Minor students hurl bombs at birthday party in Prayagraj

Minor students hurl bombs at birthday party in Prayagraj
On receiving information about the incident, SP City Dinesh Kumar Singh, along with police force, reached the spot. The injured youths were sent to the hospital for treatment and the matter is being investigated.

Minor students hurl bombs at birthday party in Prayagraj

Border, Kandi areas to be developed: Punjab CM

Border, Kandi areas to be developed: Punjab CM
The Chief Minister said the government is fully sensitive towards checking cross-border infiltration in Punjab. He said Punjab Police is constantly in touch with the Border Security Force (BSF) and other agencies for this purpose.

Border, Kandi areas to be developed: Punjab CM