Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

Punjab CM hands over cheque for Rs 1 crore to martyr's family

Punjab CM hands over cheque for Rs 1 crore to martyr's family
The Chief Minister said his government is always at hand to help and support the family. He said the countrymen would always remain indebted to Jawan Kuldeep Singh, who attained martyrdom to safeguard the security and sovereignty of the country.

Punjab CM hands over cheque for Rs 1 crore to martyr's family

Droupadi Murmu will make an outstanding President: PM

Droupadi Murmu will make an outstanding President: PM
In a series of tweets, the Prime Minister said: "India scripts history. At a time when 1.3 billion Indians are marking Azadi Ka Amrit Mahotsav, a daughter of India hailing from a tribal community born in a remote part of eastern India has been elected our President! Congratulations to Smt. Droupadi Murmu Ji on this feat."

Droupadi Murmu will make an outstanding President: PM

Broken mobile phone, ammunition & pharma opioids seized from Moosewala killers: Official

Broken mobile phone, ammunition & pharma opioids seized from Moosewala killers: Official
The shooters were hired by jailed gangster Lawrence Bishnoi, the main conspirator who confessed that the execution planning of Moosewala was hatched in August last year to avenge the murder of Vicky Middukhera.

Broken mobile phone, ammunition & pharma opioids seized from Moosewala killers: Official

60 pilots, 150 cabin crew failed breathalyzer test

60 pilots, 150 cabin crew failed breathalyzer test
The compliance of the action taken by the operator is verified during the next audit and surveillance. In case of any violations or non-compliance to regulations detected during audit and surveillance, enforcement action including financial penalty is imposed by the DGCA.

60 pilots, 150 cabin crew failed breathalyzer test

Delhi Police use water cannons to disperse protesting Cong workers

Delhi Police use water cannons to disperse protesting Cong workers
Former Union Minister P. Chidambaram said his party is protesting the ED summons to Sonia Gandhi. "The AJL-Young India transaction is recorded in the books of account, the returns filed by the two companies and in the Income Tax returns. All that the ED wants to know can be found in the records," he said.

Delhi Police use water cannons to disperse protesting Cong workers

Punjab will be soon free of gangsters: Bhagwant Mann

Punjab will be soon free of gangsters: Bhagwant Mann
During a meeting with Punjab DGP Gaurav Yadav and other officers, who called on him at his official residence here, Mann said that gangsters and drug peddlers were patronised by the previous governments.

Punjab will be soon free of gangsters: Bhagwant Mann