Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

1300 kg firecrackers seized in Delhi

1300 kg firecrackers seized in Delhi
Delhi Police has apprehended three men and seized approximately 1,300 kilograms of firecrackers from their possession. In view of the ban in Delhi, the accused allegedly procured the firecrackers from neighbouring Gurugram. The accused identified as Yogender (62), Kishan Lal (60), both residents of Kotala Mubarakpur, and Akash Vashishith (35), a resident of Malviya Nagar, had procured the stock of firecrackers from Farukhnagar near Gurugram. 

1300 kg firecrackers seized in Delhi

CBI charge sheets 6 in Manipur viral video case

CBI charge sheets 6 in Manipur viral video case
The Central Bureau of Investigation (CBI) on Monday filed a charge sheet against six accused and a report against one child in conflict with law in connection with the May 4 viral video case in Manipur, involving sexual assault on women and killing of two men. It filed a charge sheet against six accused and a report against one child in conflict with the law (CCL) before the special CBI court here.  

CBI charge sheets 6 in Manipur viral video case

Four killed, 30 injured as 23 coaches of North East Express derail in Bihar

Four killed, 30 injured as 23 coaches of North East Express derail in Bihar
The Railways on Thursday confirmed that four passengers have died and 30 others injured in the derailment of the North East Express train in Bihra's Buxar district. Following the accident, East Central Railway GM Tarun Prakash, Danapur DRM Jayant Kumar Chaudhary and other officers reached Raghunathpur to take control of the situation. The technical teams initiated investigation of the mishap.

Four killed, 30 injured as 23 coaches of North East Express derail in Bihar

Impersonation heist: Fake traffic cops decamp with Rs 50 L in Delhi robbery

Impersonation heist: Fake traffic cops decamp with Rs 50 L in Delhi robbery
Impersonating as traffic police, four men robbed a Pan Bahar Pvt Ltd employee of Rs 50 lakh here while he was returning after collecting a payment, an official said on Thursday. The incident occurred on Wednesday evening near Salim Garh flyover on the Outer Ring road.

Impersonation heist: Fake traffic cops decamp with Rs 50 L in Delhi robbery

New possibilities being created for youth as unemployment decreasing fast: PM Modi

New possibilities being created for youth as unemployment decreasing fast: PM Modi
Prime Minister Narendra Modi on Thursday said that new possibilities are being created for the youth as India's economy is expanding and unemployment is decreasing fast in India. In a virtual address at Kaushal Dikshant Samaroh 2023, the Prime Minister said that employment creation in India has reached a new height and the unemployment rate in India is at its lowest level in six years according to a recent survey.

New possibilities being created for youth as unemployment decreasing fast: PM Modi

SC reserves verdict on pleas filed against remission granted to convicts in Bilkis Bano case

SC reserves verdict on pleas filed against remission granted to convicts in Bilkis Bano case
The Supreme Court on Thursday reserved its verdict on a batch of petitions filed against the early release of convicts in the Bilkis Bano case by the Gujarat government. A bench of Justices B.V. Nagarathna and Ujjal Bhuyan reserved the judgment after hearing both the sides on the question of validity of the remission orders setting free convicts in the case of the gang-rape of Bano and murder of her family members committed during the 2002 post-Godhra riots.

SC reserves verdict on pleas filed against remission granted to convicts in Bilkis Bano case