Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

Post twin towers demolition, 45 lakh litres water used to remove dust

Post twin towers demolition, 45 lakh litres water used to remove dust
According to the information received from the authority, the capacity of a tanker is about 10,000 litres. In such a situation, 45 lakh litres of water has been used so far. Work is still going on at many places. As thick layer of dust had accumulated all around, especially in the surrounding green belt, work for removing it from the trees and roads is in full swing. 

Post twin towers demolition, 45 lakh litres water used to remove dust

Pizza delivery man shot for refusing to accept torn note

Pizza delivery man shot for refusing to accept torn note
The victim, Sachin Kashyap, was rushed to a district hospital, from where he was taken to a specialised medical centre in Bareilly.  His condition is said to be critical. SHO of Sadar Bazar, Amit Pandey said an FIR has been registered against the accused, Nadeem Khan, 27 and his brother Naeem, 29.

Pizza delivery man shot for refusing to accept torn note

Punjab Cabinet gives nod to new food grains labour policy

Punjab Cabinet gives nod to new food grains labour policy
The revised transportation policy mandates, for the first time ever, the installation of vehicle tracking systems in every vehicle used for transportation of food grains procured by the government.

Punjab Cabinet gives nod to new food grains labour policy

Moosewala murder: Punjab Police name 36 in charge sheet

Moosewala murder: Punjab Police name 36 in charge sheet
Besides Bishnoi and Jaggu Bhagwanpuria, the others who have been named in the charge sheet include Manmohan Mohana, Deepak Tinu, Sandeep Kekda, Ankit Sirsa, Priyavrat Fauji, Sachin Bhiwani, Keshav, Kashish, Manpreet Manu, and Jagroop Roopa.

Moosewala murder: Punjab Police name 36 in charge sheet

Three days after mysterious death, Sonali Phogat cremated in Haryana

Three days after mysterious death, Sonali Phogat cremated in Haryana
Her 16-year-old daughter, Yashodhara, lit the funeral pyre amid the presence of a large number of people and leaders who turned up to pay their last respects. The family demanded a probe into her death at a resort in Goa by the CBI.

Three days after mysterious death, Sonali Phogat cremated in Haryana

UP youth critical after being set afire by girlfriend's family

UP youth critical after being set afire by girlfriend's family
According to reports, Ankit had gone to meet the girl, late on Tuesday night. The girl's family members came to know and locked up Ankit in a room. "The family called other relatives and they all poured petrol on the boy and set him on fire. As he began screaming, they drove him out of their house and started shouting that the victim had attacked their house with a petrol bomb," said a source.

UP youth critical after being set afire by girlfriend's family