Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

Oust traditional parties from Himachal, says Punjab CM

Oust traditional parties from Himachal, says Punjab CM
The Chief Minister, accompanied by Delhi Deputy Chief Minister Manish Sisodia, said that by playing musical chairs, the traditional parties have mercilessly plundered the wealth of the state, and have connived with each other to shield their misdeeds. 

Oust traditional parties from Himachal, says Punjab CM

Air India 'kicks off' direct flights to Doha from key cities as Qatar prepares to host football extravaganza

Air India 'kicks off' direct flights to Doha from key cities as Qatar prepares to host football extravaganza
The flights, to be introduced from October 30, will connect Mumbai, Hyderabad and Chennai with Qatar's capital Doha during this period. 13 flights per week will operate from Mumbai, four from Hyderabad and three from Chennai. These flights will be in addition to the existing daily flights to Doha from Delhi.

Air India 'kicks off' direct flights to Doha from key cities as Qatar prepares to host football extravaganza

Three students detained in Amritsar for bomb hoax message

Three students detained in Amritsar for bomb hoax message
Acting swiftly on the complaint of the principal, the security was stepped up at the school by deploying commandos and sniffer dogs. During the probe, the police found it an act of mischief by three students of the school.

Three students detained in Amritsar for bomb hoax message

Punjab Police bust ISI-backed terror module

Punjab Police bust ISI-backed terror module
The DGP said the arrested persons include the prime perpetrator of planting an improvised explosive device (IED) at Shahabad in Haryana recently, who has been identified as Nachhatar Singh, alias Moti, a resident of Tarn Taran.

Punjab Police bust ISI-backed terror module

'Practices of Sikhism well ingrained in culture of country, comparison incorrect', SC on Hijab row

'Practices of Sikhism well ingrained in culture of country, comparison incorrect', SC on Hijab row
A bench comprising justices Hemant Gupta and Sudhanshu Dhulia told advocate Nizam Pasha, representing a petitioner, that the comparison with Sikhs may not be proper and the 5 Ks of Sikh have been held to be mandatory.

'Practices of Sikhism well ingrained in culture of country, comparison incorrect', SC on Hijab row

Queen Elizabeth II will be remembered as 'stalwart of our times': PM Modi

Queen Elizabeth II will be remembered as 'stalwart of our times': PM Modi
Prime Minister Modi recalled his meeting with Queen Elizabeth II during the UK visit in subsequent tweet and said, "I had memorable meetings with Her Majesty Queen Elizabeth II during my UK visits in 2015 and 2018. I will never forget her warmth and kindness. During one of the meetings she showed me the handkerchief Mahatma Gandhi gifted her on her wedding. I will always cherish that gesture".

Queen Elizabeth II will be remembered as 'stalwart of our times': PM Modi