Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

Visa issues will be solved by year-end, Australia tells India

Visa issues will be solved by year-end, Australia tells India
The visa backlog issue is of utmost concern to the Indian students who are trying to return to educational institutions in Australia following the Covid pandemic. Jaishankar, who is on his second visit to Australia, said he was assured that the situation has improved and about 77,000 Indian students are back in Australia.

Visa issues will be solved by year-end, Australia tells India

Two more aides of Lawrence Bishnoi gang held in Delhi

Two more aides of Lawrence Bishnoi gang held in Delhi
Deputy Commissioner of Police (DCP) of Special Cell, Jasmeet Singh said that the arrested gangsters, identified as Deepak Arora alias Deepa alias Popat and Gulshan Kumar alias Gulia, were arrested from the Lado Sarai area in the national capital.

Two more aides of Lawrence Bishnoi gang held in Delhi

Punjab and Haryana HC quashes FIRs against Bagga, Vishwas

Punjab and Haryana HC quashes FIRs against Bagga, Vishwas
BJP leader Bagga had moved the High Court while challenging the non-bailable arrest warrant issued against him by a Mohali Court in May. While pronouncing the judgment in Bagga case, Justice Anoop Chitkara said the court had seen all the tweets and posts placed on record by the parties.

Punjab and Haryana HC quashes FIRs against Bagga, Vishwas

Avoid non-essential travel, India advises its nationals in Ukraine

Avoid non-essential travel, India advises its nationals in Ukraine
In view of the current escalation of hostilities in Ukraine, Indian nationals are advised to avoid all non-essential travel to and within Ukraine. They must strictly follow the safety and security guidelines issued by the Ukrainian Government and local authorities, the advisory said.

Avoid non-essential travel, India advises its nationals in Ukraine

India logs 1,957 new Covid cases, 8 deaths

India logs 1,957 new Covid cases, 8 deaths
India reported 1,957 fresh Covid cases in the last 24 hours, against 2,424 Covid cases recorded on the previous day, said the Union Health Ministry on Tuesday.  In the same period, the country has recorded 8 more Covid related deaths, taking the death toll to 5,28,822 as per the report.

India logs 1,957 new Covid cases, 8 deaths

Akali Dal chief warns Punjab CM against negotiating on river water

Akali Dal chief warns Punjab CM against negotiating on river water
Badal's assertions come in the wake of Haryana Chief Minister Manohar Lal Khattar saying that he will be meeting his Punjab counterpart regarding the Sutlej-Yamuna Link (SYL) canal on October 14 in Chandigarh.

Akali Dal chief warns Punjab CM against negotiating on river water