Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

Two foreigners held with heroin in separate operations in Dwarka

Two foreigners held with heroin in separate operations in Dwarka
Police said that with the arrest of the duo, identified as Samual Uzochukwu Nnowaruom and Joseph Ebekue, both from Nigeria, the entire backbone of the drug peddling syndicate has been broken in Dwarka area.

Two foreigners held with heroin in separate operations in Dwarka

Death toll in Morbi bridge collapse reaches 141: Police official

Death toll in Morbi bridge collapse reaches 141: Police official
The toll was confirmed to the media by Rajkot Range Inspector General of Police Ashok Yadav. However, the toll according to the Minister of State for Home Harsh Sanghavi is 132, while two persons remain unaccounted for.

Death toll in Morbi bridge collapse reaches 141: Police official

People of Gujarat will end 27-year of corrupt regime: Punjab CM

People of Gujarat will end 27-year of corrupt regime: Punjab CM
Addressing to a gathering here, Mann said it is crystal clear that the people of Gujarat have made up their mind to give mandate in favour of AAP by ousting the BJP from the power. He said the Opposition is trying to malign AAP by dubbing it 'B' team of others but AAP is party of Gujarat's people and 130 crore of Indians.

People of Gujarat will end 27-year of corrupt regime: Punjab CM

Four shooters of Bambiha gang arrested in Punjab

Four shooters of Bambiha gang arrested in Punjab
Mining trader Mehal Singh (70) was shot dead outside his house on October 13. The operation was jointly carried out by the Anti-Gangster Task Force (AGTF), Counter Intelligence (CI) Punjab, the District Police of Udham Singh Nagar Uttarakhand, the Special Cell Delhi and the District Police of Mohali.

Four shooters of Bambiha gang arrested in Punjab

Woman going to celebrate Bhai Dooj dies after being attacked by scooty-borne robbers

Woman going to celebrate Bhai Dooj dies after being attacked by scooty-borne robbers
The deceased identified as Sunita Mittal was travelling by an e-rickshaw. Her grandson and daughter-in-law were also with her. She was on her way to Rohini sector 9. In the Prashant Vihar area two persons who were riding on a scooty attacked her in a bid to snatch her bag. The woman raised an alarm.

Woman going to celebrate Bhai Dooj dies after being attacked by scooty-borne robbers

Two Indian women held at Mumbai airport with gold hidden in jeans

Two Indian women held at Mumbai airport with gold hidden in jeans
During the physical search, both the women were detected with something wrapped below their knees in a bandage-like arrangement, arousing suspicions. On further examination, it was found that the duo had wrapped 24 carat pure gold in wax form around their legs, concealed with an adhesive bandage-like material underneath their jeans.

Two Indian women held at Mumbai airport with gold hidden in jeans