Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

Punjab CM acts tough on Kotkapura killing incident, directs police to nab culprits

Punjab CM acts tough on Kotkapura killing incident, directs police to nab culprits
During the meeting, the police officers briefed the Chief Minister about the incident. Dera Sacha Sauda follower, Pradeep Singh, was shot dead by five unidentified men in Punjab's Kotkapura town on Thursday.

Punjab CM acts tough on Kotkapura killing incident, directs police to nab culprits

Tremors felt in Lucknow, parts of UP as 6.3-magnitude earthquake hits Nepal

Tremors felt in Lucknow, parts of UP as 6.3-magnitude earthquake hits Nepal
There was panic in several areas and people stayed out of their homes for nearly two hours after the tremors were felt. The tremors lasted for nearly 10 seconds and were reported from several parts of the state.

Tremors felt in Lucknow, parts of UP as 6.3-magnitude earthquake hits Nepal

Fake call centre busted in Delhi, 12 arrested

Fake call centre busted in Delhi, 12 arrested
Delhi Police have busted a fake call centre in Delhi's Uttam Nagar which scammed more than 1700 people on the pretext of providing them loans and arrested 12 people in this connection, an official said on Wednesday.  Police said that the fake call centre was disguised as a medicine supply store.

Fake call centre busted in Delhi, 12 arrested

3 held for smuggling gold at Chennai, Delhi airports

3 held for smuggling gold at Chennai, Delhi airports
In the first case, Customs officials in Chennai said on Wednesday that they have arrested two persons for smuggling gold worth Rs 1.33 crore. Both the passengers, who came to Chennai from Muscat, were held on Tuesday.

3 held for smuggling gold at Chennai, Delhi airports

Tuition fee should always be affordable, education not a business: SC

Tuition fee should always be affordable, education not a business: SC
A bench of Justices M.R. Shah and Sudhanshu Dhulia said to enhance the fee unilaterally would be contrary to the objects and purpose of Andhra Pradesh Educational Institutions (Regulation of Admissions and Prohibition of Capitation Fee) Act, 1983 as well as the Rules, 2006 and the decision of this court in the case of P.A. Inamdar. 

Tuition fee should always be affordable, education not a business: SC

Punjab may witness 20pc rise in aerosol pollution in 2023: Study

Punjab may witness 20pc rise in aerosol pollution in 2023: Study
The study -- A deep insight into state-level aerosol pollution in India -- by researchers Abhijit Chatterjee Associate Professor and his PhD scholar Monami Dutta from Bose Institute, Kolkata, provides a national scenario of aerosol pollution with the long-term (2005-2019) trend, source apportionment, and future scenario (2023) for various Indian states.

Punjab may witness 20pc rise in aerosol pollution in 2023: Study