Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

Punjab DGP orders quarterly inspection of gun houses

Punjab DGP orders quarterly inspection of gun houses
Punjab has only two per cent of India's population, while it has nearly 10 per cent of the total licensed weapons which stand at nearly 4 lakh, or 13 gun licenses for every 1,000 persons in the state.

Punjab DGP orders quarterly inspection of gun houses

AAP govt in Punjab on borrowing spree: Akali Dal

AAP govt in Punjab on borrowing spree: Akali Dal
The Shiromani Akali Dal on Friday asked the Aam Aadmi Party government in Punjab to list development works initiated by it as well as disclose capital assets created to justify the "unprecedented" borrowing of Rs 39,200 crore for nine months of the current fiscal with Rs 14,700 crore being borrowed for the third quarter. 

AAP govt in Punjab on borrowing spree: Akali Dal

Mehrauli Murder: Shraddha was physically assaulted multiple times by Aftab

Mehrauli Murder: Shraddha was physically assaulted multiple times by Aftab
Shraddha, who was beaten up and strangled to death and then chopped into 35 pieces by Aftab, had conversations with her friends and a co-worker either on WhatsApp or Instagram. She had told them that she has been physically assaulted by Aftab since the beginning of their relationship.

Mehrauli Murder: Shraddha was physically assaulted multiple times by Aftab

Indian national jailed in Singapore for bank fraud

Indian national jailed in Singapore for bank fraud
Bhambri Kunal, 26, who first came to Singapore in 2018 to study, pleaded guilty to three counts of dealing with the benefits of criminal conduct. In exchange for at least $100, Kunal, who was jailed on Wednesday, withdrew cash totalling more than $26,000 from Singapore bank accounts.

Indian national jailed in Singapore for bank fraud

SKM urges farmers to continue struggle till all demands are met

SKM urges farmers to continue struggle till all demands are met
Earlier, on November 14, SKM's National Council held a meeting at Gurudwara Rakabganj and strongly condemned the Modi government for betraying the farmers by not implementing the written assurances made on December 9, 2021 for legally guaranteed MSP, withdrawal of the Electricity Bill, among other demands. 

SKM urges farmers to continue struggle till all demands are met

Mehrauli murder case: Aftab Poonawala's police custody extended for five more days

Mehrauli murder case: Aftab Poonawala's police custody extended for five more days
The investigators doubted his version and on strong questioning and through digital evidences, including the use of her Instagram account, which showed the location of the Mehrauli area, Poonawalla finally confessed to killing the victim and then chopping her body into 35 pieces and was arrested on November 12.

Mehrauli murder case: Aftab Poonawala's police custody extended for five more days