Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

Darpan News Desk IANS, 24 Nov, 2023 06:06 PM
  • Mumbai-Ahmedabad bullet train project: 100 km of viaducts, 250 km pier work completed

New Delhi, Nov 24 (IANS) The National High Speed Rail Corporation Limited (NHSRCL) said that 100 km of viaducts were ready for the 508 km of the mega Mumbai-Ahmedabad High Speed Rail Corridor project while 250 km of pier work has been completed.

The NHSRCL said that on November 25, 2021 first girder was launched while the first km of viaduct was completed on June 30, 2022 in a span of six months.

The completion of 50 km of viaduct was completed in a span of 10 months on April 22, 2023 and 100 km in the next six months, it said.

It said that the project achieved this milestone of construction of cumulative 100 km of viaducts through launching of 40 m long full span box girders and segmental girders.

The corporation said the full span launching technique (FSLM), where 40 meters long box girders are launched through state-of-the-art launching equipment, are being used along with Span by Span launching of segments.

"FSLM is 10 times faster than the launching through Span by Span method, which is normally used for constructing metro viaducts," the NHSRCL said, which is looking at the construction of India's first Bullet train project.

The NHSRCL also said that the 250 km of pier work has also been completed for the project

"The viaducts include bridges over Six rivers -- Par in Valsad district, Purna in Navsari district, Mindhola in Navsari district, Ambika in Navsari district, Auranga in Valsad district and Venganiya Navsari district, all in Gujarat.

"Even the installation of noise barriers has already started on the constructed viaduct."

The NHSRCL also said that the laying of first Reinforced Concrete (RC) track bed for the MAHSR corridor track system as used in Japanese Shinkansen has also started in Gujarat's Surat.

"This is for the first time, the J-slab ballastless track system is being used in India," it said.

Giving more update on the project, the corporation said, "Breakthrough of first mountain tunnel of 350 metre has been completed in Gujarat's Valsad district and even the first steel bridge of 70 m length has been erected in Gujarat's Surat.

"This is the first of the 28 steel bridges which will be part of the MAHSR corridor," the NHSRCL said.

The foundation stone for India's first Mumbai-Ahmedabad High Speed Rail Project was laid in September 2017 by Prime Minister Narendra Modi and his then Japanese counterpart Shinzo Abe.

The project is scheduled to be completed by 2026.

MORE India ARTICLES

Akali Dal opposes Haryana's proposal to establish Assembly in Chandigarh

Akali Dal opposes Haryana's proposal to establish Assembly in Chandigarh
Reacting to a submission made to the UT Administrator by the Haryana Assembly Speaker, the Shiromani Akali Dal (SAD) leader in a letter to the Administrator said Chandigarh was an inalienable part of Punjab and the Haryana government could not apply for a land swap without taking the consent of the parent state.

Akali Dal opposes Haryana's proposal to establish Assembly in Chandigarh

Punjab Police arrest sixth shooter in targeted killing case

Punjab Police arrest sixth shooter in targeted killing case
Director General of Police Punjab Gaurav Yadav identified the arrested accused as Ramjan Khan, alias Raj Hooda. He said police teams have also arrested his two accomplices -- Happy Mehla (19) and Sahil Mehla (18), both resident of Hanumangarh in Rajasthan.

Punjab Police arrest sixth shooter in targeted killing case

Drugs worth Rs 50 cr seized in Assam, 5 held

Drugs worth Rs 50 cr seized in Assam, 5 held
In Cachar, three people were arrested with 1.80 lakh tablets used for intoxication on Sunday in the Lakhipur area in the district. Police informed that the international market value of seized tablets is around Rs 50 crore. The accused were identified as Abdul Saeed, Ibazur Rahman and Sameer Alam, all residents of the Cachar district.

Drugs worth Rs 50 cr seized in Assam, 5 held

Shraddha murder case: Aftab to be taken for medical check-up, Narco test likely today

Shraddha murder case: Aftab to be taken for medical check-up, Narco test likely today
Further, police teams have been sent to Tosh in Himachal Pradesh after it was revealed that he, along with his live-in partner, had stayed there for quite a long time. Aftab had strangled his live-in partner Shraddha Walkar on May 18 and then chopped her body into many pieces.

Shraddha murder case: Aftab to be taken for medical check-up, Narco test likely today

Punjab Cabinet approves implementation of old pension scheme

Punjab Cabinet approves implementation of old pension scheme
Disclosing this here today, a spokesperson for the Chief Minister's Office said the government has approved the OPS for its employees currently covered under New Pension Scheme (NPS), fulfilling a long-pending demand of employees of the state.

Punjab Cabinet approves implementation of old pension scheme

Over 30 students at Hyderabad college fall ill due to suspected gas leak

Over 30 students at Hyderabad college fall ill due to suspected gas leak
The affected girl students of Kasturba Gandhi College in West Maredpally, Secunderabad were hospitalised with complaints of breathlessness and dizziness. The college authorities denied that there was any gas leak from college lab. They said foul smell from garbage dump on the college boundary wall led to students falling ill.

Over 30 students at Hyderabad college fall ill due to suspected gas leak